HSS Logo Department of Energy Seal
Left Tab SEARCH Right Tab TOOLS Right Tab Left Tab HOME Right Tab Left Tab ABOUT US Right Tab Left Tab FUNCTIONS Right Tab Left Tab RESOURCES Right Tab Left Tab NEWSFEEDS Right Tab Left Tab VIDEOS Right Tab Left Tab EVENTS
Environmental Protection, Sustainability Support & Corporate Safety Analysis
HS-20 Home
Mission & Functions
Program Contacts
What's New?
Sustainability Support
Environment
Corporate Safety Programs
Analysis
Environment
Environmental Policy
Environmental Guidance
Environmental Reports
Environmental Management System
Radiation Protection
Environmental Compliance
Environmental Justice
Environmental Training
Environmental Tools
Search Our Documents
Topics & Resources
Air
CERCLA
Cultural & Natural Resources
DOE Comments on Rulemakings
Federal Environmental Laws
Envirosearch
Institutional Controls
NEPA Activities
RCRA
RQ•Calculator
Water
HSS Logo

Module 2: Emergency Planning Notification

 
Return
 
Steps 9 and 10
         
   
 
   
   

One-Time Reporting Requirements

   
         
   
 
   
    This section of Module 2 describes one-time reporting requirements, unless updates are required (see Step 14).    
         
         
    Step 11
 
Notify the State Emergency Response Commission (SERC) that the facility has present an amount of EHS that is greater than or equal to its TPQ. This notification can be accomplished through a letter.
 
An example of a letter to the SERC is provided. PDF File - SERC Notification Letter
   
   
arrow
   
         
    Step 12
 
Designate a person at the facility to be the facility emergency planning coordinator. This person will act as a liaison with the Local Emergency Planning Committee (LEPC).
   
   
arrow
   
         
    Step 13
 
Notify the LEPC that the facility has present an amount of EHS that is greater than or equal to its TPQ and provide the LEPC with the identity of the facility emergency planning coordinator. Thsi notification can be accomplished through a letter.
 
An example of a letter to the LEPC is provided. PDF File - LEPC Notification Letter
   
   
arrow
   
         
    Step 14
 
At this point, the facility's Emergency Planning Notification responsibilities are complete until the LEPC requests additional information or changes occur at the facility which affect emergency planning.
   
         