|
DOE/EH-0127 --- Issue No. 90-03 --- 04/90
Coordinating Construction/Maintenance Plans with Facility Manager May Deter Unexpected Problems and Accidents
Recently, two staff members at a DOE facility were exposed to toxic times when
combustion products from burning fiberglass insulation entered an air intake
plenum. The incident occurred when contractor construction personnel who were
working near the air intake plenum inadvertently burned some of the adjacent
fiberglass insulation material with an oxygen- acetylene cutting torch. Fumes
from the burning material entered the air intake plenum and were dispersed
into the building.
Although this incident could have resulted in a significant health hazard for
those in the affected area, no such problems were noted, and none of the staff
became ill -- probably because of the relatively small amount and low
concentration of fumes. However, the fumes did have a negative impact on a
research project underway in the laboratory. Because the results of the
experiment in progress could have been affected by the fumes, the project had
to be terminated -- an action that resulted in a $17,000 loss.
Lessons Learned/Actions Taken
Following this incident, an investigation board was appointed to determine
what had caused the problem and recommend corrective actions to ensure that
similar incidents would not occur in the ftiture. The board determined that
the primary cause of the incident was a lack of coordination between those
involved in planning and carrying out construction activities and the
appropriate facility personnel (in this case, the building manager). If the
building manager had been aware of the construction work, he probably would
have been able to take the appropriate protective measures.
On the basis of information gathered during the investigation into this
incident, numerous corrective actions were formulated at the facility where
the incident occurred. Although all of these corrective actions may not be
applicable to other DOE facilities, they are listed below for information
purposes. The actions should be reviewed at all DOE facilities for their
applicability and implemented as deemed necessary.
- Determine the potential consequences of planned construction/maintenance
activities on operating systems and on nearby areas, and ensure that the
work packages or specifications developed prior to construction or
maintenance take these consequences into consideration.
- Prepare check lists to assist field engineers and building managers in
evaluating specifications and in planning work activities. Such a
checklist will ensure that someone who is familiar with site facilities and
systems is providing surveillance of the work and related activities.
- Provide additional training to field engineers and building managers. This
training should stress the following:
- need for good communication between
the field engineer and construction forces and between the field engineer
and the building manager with regard to work plans and daily work
activities
- potential for operating problems and possible need for special work
restrictions, plans, check/hold points, etc.
- importance of effective real-time communications during on-going
activities
- use (and fulfillment of intent) of required permits
- Develop a program to ensure that field engineers assigned to work around
critical operating equipment/systems have the appropriate training and
experience.
- Establish criteria for determining when formal plans/procedures for
acceptance testing of field work are required.
- Schedule periodic meetings for building and operations managers where the
potential impact of upcoming building and equipment modifications on other
facility programs can be discussed and planned for.
- Ensure that interim or replacement staff are prepared and qualified for the
responsibilities of building management.
- Stress the need for heightened awareness of the impact of
construction/maintenance and other building operations on occupant safety,
and provide information to ensure the proper response to abnormal events.
- Prepare guidance for building managers on scheduling periodic meetings with
operations managers to discuss the potential impact of upcoming building
and equipment modifications.
- Provide information to appropriate managers regarding the need for
heightened awareness of building occupants toward building operations and
the possible impact of such operations on occupant safety and occupant
response to off-normal events.
Conclusion
Routine facility construction and maintenance activities can sometimes have
unexpected outcomes. And, if these activities are not properly planned and
implemented, the outcome may be a safety or health hazard for facility
personnel, damage to the facility, or a negative impact on facility
activities. All DOE facilities should have a formal method to ensure that
building/facility management approves the startup and closeout of work and
that they are updated on the status of work in progress. In addition, any
health and safety concerns should be identified and planned for during the
preparation of work packages.
This publication is one of several series of bulletins published so that DOE
program managers and contractors can share information about potential
occupational safety problems relevant to DOE operations. For more information
or additional copies, contact Eleanor Crampton, Performance Evaluation
Division, Office of Safety Compliance, Assistant Secretary for Environment.
Safety & Health, U.S. Department of Energy, Washington, DC 20545; telephone
(301)390-3732.
|