HSS Logo Department of Energy Seal
Left Tab SEARCH Right Tab TOOLS Right Tab Left Tab HOME Right Tab Left Tab ABOUT US Right Tab Left Tab FUNCTIONS Right Tab Left Tab RESOURCES Right Tab Left Tab NEWSFEEDS Right Tab Left Tab VIDEOS Right Tab Left Tab EVENTS
Office of Nuclear Safety
Office of Nuclear Safety Home
Readiness Reviews
Readiness Reviews Home
Applicable Directives, Standards, & Handbooks
Start Up Notifications, Plan of Actions, and Implementation Plans
Functional Area CRADS
Training
425.1D Implementation Procedures
Achieving Readiness
Lessons Learned
Readiness Archives
Library
HSS Logo

Generic Lessons Learned That Apply to the Design, Construction, Operation, and Decommissioning of DOE Facilities


During startup of new facilities, numerous cases have been observed in which the surveillance requirement supporting the safety basis could not be completed, or if completed, did not properly verify the safety basis requirement. Surveillance procedures should be completed, validated, and executed as part of the startup program, prior to the implementation of the supported Technical Safety Requirements (TSRs). Actually executing the surveillance will reveal such problems as: test points that are not installed; test points that are inaccessible; and other interfering interlocks or functions. These problems have occurred repeatedly in previous ORR/RAs.

Additionally, determination must be made that the surveillance actually tests the function or protective action upon which the safety basis depends. Previous ORR/RAs have revealed numerous occasions in which surveillances have been conducted and through either invalid acceptance criteria or a misunderstanding of the as-built configuration, the surveillance did not test the required functions.

For further information or comments on the ORR web site, please contact James M. Heffner.