Rec. 99-1 Safe Storage of Fissionable Material called "Pits"
- Board Recommendation: from Chairman Conway to Secretary Richardson,
dated August 11, 1999. [HTML] [WP]
[PDF]
- Department Response: from Secretary Richardson to Chairman Conway,
dated October 12, 1999. [HTML] [WP]
[PDF]
- Department Implementation Plan, dated February 1, 2000. [HTML]
- Board Closure: dated September 9, 2005 [HTML]
[DOC] [PDF]

No document links for 2009
|
No document links for 2008
|
No document links for 2007
|
No document links for 2006
|
- September 9, 2005, Board letter establishing an annual reporting requirement regarding the Pit Management Plan (PMP) and the pit packaging program at Pantex and closing Recommendation 99-1, Safe Storage of Fissionable Material Called "Pits". [HTML] [PDF] [DOC]
- August 8, 2005, Department letter forwarding the Final Report regarding the 99-1 implementation plan, Safe Storage of Fissionable Materials Called "Pits", and proposing closure of the 99-1 recommendaton. [HTML] [PDF] [DOC]
|
No document links for 2004
|
No document links for 2003
|
- May 8, 2002, Board letter regarding the Department's revision to the Implementation Plan for Board recommendation 99-1, Safe Storage of Fissionable Material Called "Pits." [HTML] [PDF] [WPD]
- March 18, 2002, Department letter informing the Board of the Department's intent to change commitment 5.2.1 in Implementation Plan 99-1 regarding the safe storage of pits at the Pantex Plant. [HTML] [PDF] [WPD]
- February 28, 2002, Department letter enclosing the Pantex Plant Sealed Insert First Quarter Fiscal Year 2002 Summary Status Report, a deliverable under Commitment 5.2.2 of the 99-1 Implementation Plan. [HTML] [PDF] [WPD]
|
- March 15, 2001, Department letter enclosing the AL-R8 Sealed Insert pit repackaging status report for the 1st Quarter of FY 2001 in accordance with Implementation Plan 99-1.  [HTM]
- January 11, 2001, Department letter enclosing the AL-R8 Sealed Insert Container Surveillance Report for Fiscal Year 2000, a deliverable in the 99-1 Implementation Plan.  [HTM] [WPD] [PDF]
- December 1, 2000, Department letter enclosing a report on Pantex Pit Management Plan, a deliverable under Commitment 5.2.3 of Implementation Plan 99-1.  [HTM]
- November 17, 2000, Department letter enclosing a copy of the Final Change Order (FCO) for Inconel 718 capscrews to replace carbon steel capscrews in AL-R8 Sealed Insert, a deliverable under Commitment 5.1.1 of Implementation Plan 99-1.  [HTM] [WPD] [PDF]
- August 18, 2000, Department letter forwarding a copy of the Pantex Plant Sealed Insert Third Quarter FY 2000 Summary Status Report, a deliverable under Commitment 5.2.2 of implementation plan 99-1.  [HTM]
- July 7, 2000, Board letter regarding budget concerns that may preclude the Department from meeting its commitments in Implementation Plan 99-1.  [HTM] [WPD] [PDF]
- April 7, 2000, Board letter acknowledging receipt of and accepting the Department's proposed implementation plan for 99-1.  [HTM] [WPD] [PDF]
- March 27, 2000, Department letter forwarding the Department's pit storage container surveillance program plan. This is a deliverable under Commitment 5.3.1 of implementation plan 99-1.  [HTM] [WPD] [PDF]
- February 23, 2000, Department letter forwarding the amended Work Authorization Directive (WAD) for pit repackaging at the Pantex Plant. It is also a deliverable under Commitment 5.2.1 of the Department's 99-1 Implementation Plan.  [HTM]
- February 1, 2000, Department letter forwarding DOE's Implementation Plan for Board Recommendation 99-1, Safe Storage of Pits at Pantex.  [HTM]
- October 12, 1999, Department letter acknowledging
receipt and acceptance of the Board's Recommendation 99-1. [HTML]
[WP] [PDF]
- August 11, 1999, Board letter forwarding recommendation
99-1, safe storage of fissionable material called "pits." [HTML] [WP]
[PDF]

|
 |
 |
|