Rec. 96-1 In-Tank Precipitation System at Savannah River Site
- Board Recommendation: from Chairman Conway to Secretary O'Leary, dated August 14, 1996. [PDF]
- Department Response: from Secretary O'Leary to Chairman Conway, dated September 16, 1996. [PDF]
- Department Implementation Plan: dated November 12, 1996. [PDF]
- Department Closure Proposal: from Assistant Secretary Roberson to Chairman Conway, dated March 14, 2002. [PDF]
- Board Closure: from Chairman Conway to Secretary Abraham, dated March 29, 2002. [PDF]

- March 29, 2002, Board letter closing recommendation 96-1 and requesting a report on the Department's appoach for treatment and disposition of the waste in Tank 48 at Savannah River Site. [PDF]
- March 14, 2002, Department letter providing updated status on overdue Environmental Management commitments to the Board. [PDF]
- August 22, 2001, Department letter regarding removal of Tank 49 and Tank 50 from Recommendation 96-1. [PDF]
- April 25, 2001, Department letter designating Mr. Charles E. Anderson as the Responsible Manager for implementation of Recommendation 96-1. [PDF]
- August 24, 2000, Department letter regarding Recommendation 96-1 - disposition of Tank 49 material. [PDF]
- August 17, 2000, Department letter informing the Board of the designation of Mr. Ralph Erickson as the Responsible Manager for implementation of Board recommendation 96-1. [PDF]
- July 17, 1998, Department letter forwarding 96-1 implementation plan deliverables. [PDF]
- May 27, 1998, Department letter regarding suspension of restart activities at the ITP Facility per the 96-1 implementation plan. [PDF]
- May 27, 1998, Department letter forwarding a reference documents listing per the 96-1 implementation plan. [PDF]
- March 19, 1998, Department letter designating new Responsible Manager for 96-1. [PDF]
- March 3, 1998, Department forwards its program status for the 96-1 implementation plan. [PDF]
- January 16, 1998, Board letter regarding implementation plan 96-1's action plan. [PDF]
- December 23, 1997, Department letter to Board regarding
implementation plan 96-1 program status. [PDF]
- November 7, 1997, Department letter to Board regarding In-Tank-Precipitation
Facility. [PDF]
- October 31, 1997, Department forwards report on Cataytic Decomposition of Soluble
Tetraphenylborate (TPB) Studies, to update milestone 5.2.2-1 for recommendation 96-1
implementation plan. [PDF]
- October 9, 1997, Board letter forwarding and the trip reports regarding the
on-going implementation of recommendation 96-1 at the In-Tank Precipitation Facility at
Savannah River site. [PDF]
- October 3, 1997, Department letter regarding recommendation 96-1 implementation
plan. [PDF]
- July 30, 1997, Department letter providing scheduled 96-1 implementation plan
deliverable Commitment 5, Milestone 5.2.4-2. [PDF]
- June 26, 1997, Department letter providing the Board with status of the 96-1
implementation plan, signed by SROO Assistant Manager McCoy. [PDF]
- April 28, 1997, Department Rec. 96-1 Deliverable - Test Plan for Actual Waste
Confirming Studies. [PDF]
- April 2, 1997, Department letter announcing Frank McCoy as responsible manager,
signed by Assistant Secretary Alm. [PDF]
- March 10, 1997, Department letter forwarding the test summary report
for Process Verification Testing (deliverable to satisfy Commitment 3, Milestone
5.2.2-3 per the 96-1 implementation plan). [PDF]
- March 10, 1997, Department letter forwarding page change revision of Test Plan
for Catalytic Decomposition of Soluble Tetraphenylborate, signed by SROO Assistant Manager
Watkins. [PDF]
- March 5, 1997, Board letter forwarding Board technical report
DNFSB/TECH-14 Savannah River Site In-Tank Precipitation Facility Benzene Generation: Safety Implications. [PDF]
- January 28, 1997, Department letter forwarding test plan deliverables for
implementation 96-1. [PDF]
- January 28, 1997, Department letter forwarding a deliverable for implementation
96-1. [PDF]
- January 6, 1997, Board letter accepting the Department's 96-1 implementation
plan. [PDF]
- December 20, 1996, Department letter forwarding deliverable to satisfy 96-1
implementation plan milestone 5.2.2-1. [PDF]
- December 18, 1996, Department test plan for catalytic decomposition of soluble
tetraphenylborate. [PDF]
- November 12, 1996, Department letter forwarding the 96-1 implementation plan. [PDF]
- November 1, 1996, Board letter commenting on "the safety of planned conduct of experiments PFT-1 and PVT-2 at the Savannah River Site." [PDF]
- September 16, 1996, Department letter accepting Board recommendation 96-1. [PDF]
- August 14, 1996, Board letter forwarding recommendation 96-1. [PDF]

|
 |