[DOE LETTERHEAD]

 

August 18, 2008

 

The Honorable A. J. Eggenberger

Chairman

Defense Nuclear Facilities Safety Board

625 Indiana Avenue, N.W., Suite 700

Washington, D.C. 20004-2901

 

Dear Mr. Chairman:

 

Enclosed for your information is an update on the commitment made to the Defense Nuclear Facilities Safety Board (DNFSB) regarding the availability and reliability of the Device Assembly Facility (DAF) Fire Suppression System (FSS) at the Nevada Test Site. At the meeting with the DNFSB on April 17, 2008, Nevada Site Office and the Managing and Operating Contractor laid out a project plan to execute a strategy that addressed the DNFSB concerns. All major tasks to support the Project Execution Plan are proceeding as scheduled.

 

If you have any questions, please contact me or Mr. James McConnell of the Office of Safety at (202) 586-4379.

 

Sincerely,

 

Gerald L. Talbot, Jr.

Assistant Deputy Administrator

for Nuclear Safety and Operations

 

Enclosures (4):

 

1. Memo from Mellington to Talbot, Update of the Device Assembly Facility (DAF)

Fire Suppression System (FSS) Reliability Project, July 25, 2008

2. Project Execution Plan for the Device Assembly Facility Fire Suppression System,

August 1,2008

3. Presentation to DNFSB, DAF Fire Suppression System, April 17, 2008

4. Letter from DNFSB to D'Agostino, Fire Protection at the Device Assembly

Facility, January 18, 2008

cc: M. Whitaker, Jr., HS-1.1