[DNFSB LETTER HEAD]

 

February 5, 2008

 

The Honorable J. Clay Sell

Deputy Secretary of Energy

1000 Independence Avenue, SW

Washington, DC 20585- 1000

 

Dear Mr. Sell:

 

            The Defense Nuclear Facilities Safety Board (Board) bell eves that independent validation

of line management's implementation of new or substantially revised safety basis controls is

warranted for all defense nuclear facilities. The proper implementation of these controls 1nLo

equipment, procedures, and personnel training is essential to ensure that operations arc

conducted safely and within the risk envelope accepted by die Department of' Energy (DOE).

However, complex-wide requirements for conducting independent validations of control

implementations are lacking.

 

            In the past, DOE sites have conducted independent validations in many areas such DS

project design reviews, facility startup/restart operational readiness reviews, and nuclear

explosive safety studies. Some sites also conduct independent validation reviews and have

established protocols to confirm the proper implementation of safety controls derived from new

or revised Documented Safety Analyses. In a March 18, 2003, letter to the National Nuclear

Security Administration (NNSA) the Board commended NNSA’s Pantex Site Office for its

decision to perform an independent validation of the implementation of new safety basis

controls, noting that the validation effort was essential to identifying significant implementation-

related safety issues. Several sites, including the Los Alamos National Laboratory, the Y-12

National Security Complex, and Hanford Tank Farms have instituted various protocols for

independent validation of new or revised safety basis controls implementation.,

 

            While the importance of such validations is widely recognized, DOE has not issued

complex-wide requirements and guidance regarding the need and expectations for independent

validations of the implementation of new or revised safety basis controls. Independent

validation is generally performed as part of a nuclear facility startup or restart readiness reviews

in accordance with DOE Order 425.1, Startup and Restart of 'Nuclear Facilities. However,

independent validation is often omitted for new or revised controls being implemented in a

facility with ongoing operations where DOE Order 425.1 would not necessarily apply.

 

            There are a number of examples were safety controls identified by a new or revised

Documented Safely Analyses were discovered to have been inadequately implemented. The

need for independent validation reviews is clearly illustrated by such examples, which include:

 

            in place, were not fully installed.

 

            test for fire system power supplies was incorrectly specified as an “annual test” in the

            implementing procedure.

 

            safety basis inventory control for certain hazardous materials, and that shift

            management personnel lacked knowledge of new safety basis controls to effectively

            respond to certain scenarios’.

 

            Based on these findings, the Board feels it is appropriate to require independent

validation of the implementation of safety basis controls at all DOE sites. Further, the Board

believes that DOE should consider performing independent validations on a recurring basis to

ensure the facility equipment, procedures, and personnel training have not degraded over time.

Protocols at the Y- 12 National Security Complex had required re-validations every three years,

but the periodicity was recently changed to every five years. The Board considers five years as

too long a time interval for re-validation of safety controls.

 

            The Board believes the defense nuclear complex would benefit from requirements and

guidance from DOE Headquarters for independent validations of safety basis control

implementation that would capture the lessons-learned and best practices from those sites that

have conducted these reviews. Therefore, pursuant to 42 U.S.C. IC § 2286b(d), the Board requests a

report within 90 days of receipt of this letter regarding DOE’S evaluation of the need for such

requirements and guidance and any actions taken or to be taken by DOE in this area.

 

 

Sincerely,

 

A. J. Eggenberger

Chairman

 

c:

 

The Honorable James A. Rispoli

The Honorable Thomas P. D’ Agostino

Mr. Glenn S. Podonsky

Mr. Mark B. Whitaker, Jr.