[DNFSB LETTERHEAD]
June 26, 2007
To the Congress
of the United States:
In Section 3183
of the National Defense Authorization Act for Fiscal Year 2003, Congress directed
the Defense Nuclear Facilities Safety Board (Board) to conduct a study of the
adequacy of plutonium storage at the Savannah River Site (SRS). In response to the proposals made in the
Board's study, Plutonium Storage at the
Department of Energy's Savannah River Site, dated December 1, 2003, the
Board and the Secretary of Energy are required under Section 3183(d) of the
National Defense Authorization Act for Fiscal Year 2003 to submit annual
reports on the actions taken by the Secretary to address the Board's proposals.
This is the Board's fourth annual report
on the Department of Energy's (DOE) actions to address the Board's proposals
from this study.
In this study,
the Board made proposals concerning the suitability of facilities planned for
storing plutonium at the SRS, the remote monitoring and retrieval of plutonium,
and the DOE plutonium disposition program.
PROPOSALS CONCERNING THE SUITABILITY OF
FACILITIES
DOE originally
planned for extended storage of plutonium at SRS in two facilities—the K-Area Materials
Storage (KAMS) facility and Building 235-F (235-F). Both were 50-year-old facilities that did not
meet modern safety standards. The Board
proposed safety upgrades to ensure the safety, reliability, and functionality
of these facilities for plutonium storage.
Status of DOE
Actions. As noted in the previous Board
reports, DOE decided to (1) consolidate the excess plutonium currently at SRS
into the KAMS facility and (2) not use 235-F for extended storage. The Board agreed with this decision, which
obviates the need for safety upgrades to 235-F.
Subsequently, DOE reconfigured the KAMS facility such that SRS can now
consolidate all of the DOE's excess plutonium into this facility.
The Board
considered the KAMS facility to be a robust structure that could be made
suitable for extended storage by establishing an appropriate fire protection
system and eliminating unnecessary combustibles. The combustible materials of concern have been
removed. DOE is in the process of adding
a fire detection system for the storage areas in the KAMS facility and expects
to complete installation in early October 2007. The addition of this fire detection system
permits plutonium to be stored safely in the KAMS facility until dispositioned
by DOE. DOE further plans to add a
limited fire suppression system in a small analytical room in the KAMS facility
and expects to provide funding for completion of this fire suppression system
in fiscal year 2009.
PROPOSAL CONCERNING REMOTE MONITORING AND
RETRIEVAL
At the time of
the Board's initial 2003 storage study, DOE's plans for handling, moving, and shipping
a damaged, potentially contaminated container from the KAMS facility for
further disposition had not been defined and validated. The Board proposed that DOE develop and
implement validated procedures for the handling and intrasite shipment of
plutonium containers, including damaged containers. As reported in the Board's first annual report
on this subject, DOE has completed all necessary actions concerning this
proposal.
PROPOSALS CONCERNING THE PLUTONIUM DISPOSITION
PROGRAM
The Board
proposed that DOE expedite the development of a complete, well-considered plan
for the final disposition of all excess plutonium to preclude unnecessary
extended storage of plutonium at SRS. The Board also proposed that DOE conduct a new
study of available options for the storage of plutonium at SRS but DOE
subsequently decided to consolidate the SRS plutonium material into the KAMS
facility. The Board supported this
decision and, consequently, agreed the proposed study was no longer needed.
Status of DOE
Actions. Several previous National
Environmental Policy Act (NEPA) decisions have laid the groundwork for
plutonium disposition at SRS:
Based on the
approved Records of Decision for these environmental impact statements, DOE previously
chose to pursue plutonium disposition via the Mixed-Oxide Fuel Fabrication
Facility (MFFF) and a plutonium immobilization facility. As planned, this approach also envisioned some
additional plutonium disposition via the H-Canyon Facility at SRS. Although DOE cancelled its plans for the original
plutonium immobilization facility, the overall plan remains largely the same. Namely, surplus weapon-useable plutonium is to
be dispositioned via (1) the Pit Disassembly and Conversion Facility (PDCF) and
MFFF, (2) a new plutonium disposition facility, and (3) the H-Canyon Facility.
DOE continues to
pursue this so-called three-pronged approach—PDCF/MFFF, a new plutonium disposition
facility, and the H-Canyon Facility. On
August 17, 2006, the Deputy Secretary of Energy approved Critical Decision 1-A,
the selection of a preferred alternative, for the Plutonium Disposition Project.
The preferred alternative was a
plutonium vitrification process to be installed in the K-Reactor Facility at
SRS. On March 28, 2007, DOE issued a
Notice of Intent to Prepare a Supplemental Environmental Impact Statement for
Surplus Plutonium Disposition at the Savannah River Site (72 Federal Register
14,543, March 28, 2007). This
supplemental environmental impact statement will evaluate the environmental
impacts of several options, including the plutonium vitrification process as currently
defined by the three-pronged approach. DOE plans to issue a draft supplemental environmental
impact statement by January 2008.
Because of
Congressional inquiries regarding the plutonium disposition plan, DOE
commissioned a panel of experts to review the plan. The panel completed its review and issued a
report, Business Case, DOE's Proposed
Baseline Approach for Disposing of Surplus Plutonium, in April 2007. This report concludes that the three-pronged
approach will meet United States national security and nonproliferation objectives,
reduce security costs, and support DOE's efforts to consolidate nuclear
materials in the DOE complex.
Progress in
plutonium consolidation and disposition has been and continues to be slow. To date, surplus plutonium remains stored at
Hanford, Lawrence Livermore National Laboratory, and Los Alamos National
Laboratory. In its planning documents,
DOE states that future progress is subject to appropriate NEPA review and the
availability of funding.
CONCLUSION
For excess
plutonium currently at SRS, the KAMS facility will provide adequate extended storage
when the fire detection system upgrades proposed by the Board are completed by
DOE.
For excess
plutonium located at other sites, DOE has not made progress in consolidating
this plutonium at SRS because it lacks an agreed-upon disposition pathway for
excess plutonium out of the State of South Carolina. As such, each site continues to maintain its excess
plutonium inventory.
The DOE planned
disposition that utilizes MFFF, plutonium vitrification and H-Canyon Facility is
reasonable. The Board believes consolidation
of excess plutonium into a single, robust facility suitable for extended
retrievable storage is logical from a safety
perspective.
DOE should aggressively pursue consolidation
of its excess plutonium.
The Board
believes that the initial purpose of the report requested by Congress has been
satisfied. The addition of the fire
detection system permits plutonium to be stored safely in the KAMS facility
until dispositioned by DOE. Remaining
modifications to the KAMS facility are planned and straightforward. The Board will follow these modifications, as
well as DOE's effort to execute its plutonium disposition strategy.
Respectfully
submitted,
A. J.
Eggenberger
Chairman
John E.
Mansfield
Member
Joseph F. Bader
Member
Larry W. Brown
Member
Peter S. Winokur
Member