[DNFSB LETTERHEAD]
August 9, 2007
The Honorable Thomas P. D’Agostino
Administrator
National Nuclear Security
Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0701
Dear Mr. D’Agostino:
The Defense Nuclear Facilities Safety
Board (Board) has closely followed the conceptual design activities and
associated safety basis development for the Uranium Processing Facility (UPF) at the Y-12 National Security Complex (Y-12). The UPF project is awaiting formal approval of
the Critical Decision-1 (CD-1) milestone, which establishes the
preliminary project baseline range. The
overall safety strategy for the facility, which is discussed in the enclosed project summary, appears to be reasonably
conservative at CD-1. As the project progresses, the Board is
tracking a number of open items that must
be addressed early in
the preliminary
design stage to minimize project risk. The UPF project personnel provided a status of the
open items to the Board during a briefing held on
July 31, 2007. The UPF project personnel
have developed a path forward for the resolution of these items and expect them
to he resolved in the next six to nine months.
These items are listed below for your
information:
The Board recognizes that DOE has
captured some of these issues as conditions of approval in its conditional
acceptance of the Preliminary Hazard Analysis and safety design strategy. The remainder has been discussed with project
personnel.
The Board commends the safety basis
reviewers from the Y-12 Site Office for conducting a systematic analysis of
safety functions and controls developed from the contractor hazard analysis. This effort was fundamental in providing the
needed level of confidence that the identified safety controls were
sufficiently conservative for CD-1. This
systematic analysis should have been conducted by the contractor and documented
in the Preliminary Hazard Analysis.
The Board also commends DOE for
its efforts to retroactively implement the revised requirements of DOE Order
413.3A,
Program and Project Management for the Acquisition of Capital Assets, and the expectations of draft DOE Standard 1189,
Integration of Safety into the Design Process, into the conceptual design and safety
basis development for UPF.
Interaction between the Board’s staff
and UPF project personnel has been productive thus far, and the Board looks
forward to continuing this dialogue in the future.
Sincerely,
A. J. Eggenberger
Chairman
c: The Honorable William C. Ostendorff
Mr. Mark
B. Whitaker, Jr.
Mr.
Theodore D. Sherry
Enclosure
ENCLOSURE
URANIUM PROCESSING FACILITY PROJECT SUMMARY
The Uranium Processing Facility (UPF)
is planned to modernize enriched uranium processing capability at the Y-12
National Security Complex (Y-12).
This new facility will replace several
deteriorating facilities, including the 9212 Complex, and will provide a significant enhancement in the safety of Y-12 operations.
The safety design strategy for UPF during
normal operations and in accident conditions begins with the minimization or,
where possible, elimination of nuclear and hazardous materials. This is followed by the use of passive
controls to segregate nuclear materials to reduce accident consequences and
preclude a nuclear criticality. Next,
active systems are used to provide fire suppression, process safety controls,
and primary and secondary confinement of materials. The incorporation of new technologies and
lessons learned from current processing operations are expected to minimize the
use of personal protective equipment and administrative controls required for
many operations in the existing facilities.
To minimize hazardous materials, the UPF project
plans to incorporate several new technologies, some of which will also improve
the inherent safety of operations compared with the current processes in
existing Y-I 2 facilities. UPF will
utilize a new metal production process that eliminates the need to use and
store large quantities of hydrogen fluoride. The pulsed columns currently used for primary
extraction will be replaced with centrifugal contactors, which will reduce the
inventory of combustible solvents. Microwave
casting technology will replace the current casting process, which will reduce
oxide generation and improve criticality safety by not using water for cooling.
UPF was determined to be a Hazard
Category 2 facility based on the quantity of nuclear material. The project conducted a hazard analysis that
was used to develop the safety functions that the safety controls needed to
provide. Safety controls were then
initially identified based on historical knowledge of existing safety controls
at current Y-12 facilities. DOE later
performed a systematic analysis of safety functions and controls, which
identified additional safety controls. The
control set includes a safety-class fire barrier to segment
the source term in the Facility. The controls credited as safety-significant
include the following:
·
Facility
structure
·
Primary
and secondary active confinement systems
·
Fire
suppression system, including alarms, sprinkler system, plenum deluge system,
fire barriers, and the fire water supply
·
Glovebox
inerting system, including oxygen monitoring and the
ability to respond remotely to a loss of inert atmosphere
·
Criticality
accident alarm system
·
Backup
power for active
safety system
·
Material
containers for in-process storage
·
Pressure
relief for process equipment where needed
·
High-temperature
interlocks on process equipment where needed
·
Flame
management systems for process equipment where needed
·
Phase
separators for process equipment with the potential for organic-nitric
acid reactions
·
Vents
for process equipment with the potential for organic-nitric
acid reactions
·
Seismic
isolation of flammable gas lines into the facility
·
Shielding
for radiography equipment
All credited safety-class and
safety-significant controls have been preliminarily identified as being
Performance Category 3 for natural phenomena hazards. The project has identified appropriate design
criteria for the safety systems, structures, and components, including
consensus standards to be used for their design.
The project risk management plan
encompasses standard risks expected on major design and construction projects. As the project incorporated the
expectations of the draft DOE standard on integrating safety into design, the
assumptions made in developing the safety basis have been captured as specific
risks. The risks associated with issues
identified by the Board are also captured. In its safety evaluation report, DOE questioned
the adequacy of project contingency funds assigned to the risks associated with
the confinement ventilation approach and bulk chemical storage.
The project acquisition strategy calls
for issuing three architect-engineer design contracts—for mechanical process
systems, chemical process systems, and the facility. The current site contractor, BWXT, will handle
project integration, requirements management, design configuration management,
and safety basis development. To provide
real-time integration of the design efforts, BWXT plans to collocate
design personnel in one facility in the Oak Ridge area. Subsequent independent contracts for
construction will be issued following the completion of the final design stage.
DOE currently
has a Federal Project Director, who is assisted by a team of part-time personnel.
This level of staffing may not be
sufficient to provide appropriate technical oversight
of a project of this size. Of particular
concern is the ability to adequately oversee and review the process design and
safety basis development, which has been covered by two part-time individuals. DOE has developed plans to add three dedicated
personnel to the project team by the start of fiscal year 2008 to increase the
oversight of the project. The project is
in the process of developing a detailed
staffing plan.
The Project Execution Plan
comprehensively identifies the types of reviews that are expected to be
conducted during the life of the project. However, little detail is given for the design
reviews that evaluate whether safety is being integrated as early as possible
throughout each phase of the project life. The development of additional detail on the
number, scope, and scheduling of these reviews is expected in the first year of
preliminary design.
The project has developed planning for
the startup, transition to operations, and commissioning of UPF. It should
be noted that DOE’s Technical Independent Project Review Team identified that
the cost and schedule for these activities appear to be low based on recent experience
with other DOE projects and commercial experience.