[DOE LETTERHEAD]
National
Nuclear Security Administration
May 5, 2006
The Honorable A.
J. Eggenberger
Chairman
Defense Nuclear Facilities
Safety Board
625 Indiana Avenue, NW, Suite
700
Washington, D.C. 20004
Dear Mr. Chairman:
In your November 28, 2005,
letter on structural deficiencies in the 9212 complex at the Y-12 National
Security Complex (Y-l2), you requested that National Nuclear Security Administration
(NNSA) clearly
set forth the facility modifications that would be implemented should each Critical
Decision Milestone for the Uranium Processing Facility (UPF) project be delayed.
The NNSA’s long-term plan for
Enriched Uranium Operations at Y-12 is to build UPF, which will meet all code
and order requirements and significantly enhance operational efficiency while
employing new technologies and engineered controls that will substantively
reduce the risk to the public and workers. In the interim, we may have to operate 9212 up
to 15 more years to support projected mission requirements and eliminate the
backlog of nuclear materials. Our
funding strategy for Y-12 will focus on both supporting UPF project execution
and the continued safe operation of 9212 for the remainder of its anticipated
service life.
I have directed that a risk
review of the 9212 facility be completed to identify the priority list of
improvements and actions necessary to ensure continued safe operation for the next
15 years. The facility risk review will include all safety
systems, significant defense in depth systems, and process equipment vital to
the reduction of the backlog of nuclear material. The new tasking will include a prioritization
of seismic improvement, but will require additional time to complete. During the DNFSB’s March 29-30, 2006, visit to
Y-12, BWXT Y-12 and the Y-12 Site Office briefed you on these changes.
In your November 28, 2005,
letter you requested a report 60 days after completion of the risk
prioritization activity. The risk
prioritization activity was originally scheduled for completion in April 2006;
however, based on available resources we are now planning on completing the
risk prioritization activity in August 2006. We will forward the requested report to you
within 60 days of completion of the facility risk review. Should you have any questions, please do not
hesitate to contact Teresa Robbins at (865) 576-0841.
Sincerely,
Thomas P. D’Agostino
Deputy Administrator
for Defense Programs