[DOE LETTERHEAD]
National
Nuclear Security Administration
March 20, 2006
The Honorable A. J. Eggenberger
Chairman
Defense Nuclear Facilities
Safety Board
625 Indiana Ave, N.S., Suite 700
Washington, D.C. 20004-2901
Dear Mr. Chairman:
In a letter dated March 31, 2003,
the Defense Nuclear Facilities Safety Board requested that the Board members be
informed of any delays in the schedule of several projects at the Los Alamos
National Laboratory, including the Partial Site-Wide Fire Alarm Replacement and
the Waste Management Risk Mitigation Projects. Both projects were funded by Congress in
Fiscal Year 2001 to mitigate the impact of the Cerro Grande Fire and potential
future damage from similar natural disasters.
Since the first status was
reported to the Defense Nuclear Facilities Safety Board in February 2004, both
projects have made substantial progress. With the exception of three facilities, work
on all other buildings included in the Partial Site-Wide Fire Alarm Replacement
Project scope has been completed. Replacement of fire alarm panels in the Plutonium
Facility and the Chemistry and Metallurgy Research Facility has resulted in positive
Unreviewed Safety Question Determinations (USQD). The USQD package for the Plutonium Facility is
under review by the Los Alamos Site Office. The USQD package for the Chemistry and
Metallurgy Research Facility is being prepared by the Los Alamos National
Laboratory and is expected to be submitted for federal review by the end of
March 2006. As a result, the substantial
completion date for this project is now projected to be June 30, 2006.
Work on the Waste Management
Risk Mitigation Project is approximately 60 percent complete. All six fiberglass tanks have been installed
in the newly constructed underground concrete basin. Last September, Los Alamos Site Office
cancelled the contract of the general contractor responsible for this project
due to poor performance and the contractor’s inability to provide a viable
corrective action to complete the project. At the time the contract was cancelled, the
project was more than 14 months behind its baseline schedule. The Los Alamos National Laboratory has taken
over the general contractor’s responsibilities and most of the subcontractors
of the previous general contractor have stayed on the job and continue to
perform work. However, some construction
activities were recently stopped to evaluate construction quality control discovered
during an independent project review. The identified quality control issues have
been resolved and we expect to restart work before the end of March 2006.
We are in
the process of
requesting reprogramming of funds from Congress to complete the project and
request the Deputy Secretary of Energy to approve extending the project completion
date by approximately 14 months. If
approved, the project completion date will be extended to the 1st
Quarter of Fiscal Year 2008.
We will keep you and your staff
informed of any changes in the above plan and approach to complete the two
projects.
Sincerely,
Thomas D’Agostino
Deputy Administrator
for Defense Programs