September 30, 2005
The Honorable A. J. Eggenberger
Chairman
Defense Nuclear Facilities
Safety Board
625 Indiana Avenue, N.W., Suite
700
Washington, DC 20004-2901
Dear Mr. Chairman:
This is to inform you that
Commitment 211 of the Implementation Plan for
the Defense Nuclear Facilities Safety Recommendation 2000-1, Revision 2, Stabilization and Storage of Nuclear Material,
was completed on
September 27, 2005. The dissolution of
the Savannah River Site pre-existing plutonium residues has been completed in
H-Canyon. The commitment date for completion of this milestone
was September 30, 2005.
If you have any further
questions, please call me at (202) 586-0738 or call Dae Y. Chung, Acting Deputy
Assistant Secretary for Integrated Safety Management and Operations Oversight,
at (202) 586-5151.
Sincerely,
Dr. Ines R. Triay
Chief Operating Officer for
Environmental Management
cc: Mark Whitaker, DR-1
Jeffrey
Allison, SR