Dear Mr. Chairman:
In your letter of July 9, 2003,
you requested that our site offices report on the scope and periodicity of the
contractor training assessment conducted as required by Department of Energy
Order 5480.20A. In a letter dated
October 2, 2003, I indicated that the Department of Energy Livermore Site
Office would complete its training assessment of contractors by May 6, 2004. The National Nuclear Safety Administration
Service Center has notified the Livermore Site Office that they will not be
able to support that assessment until June 2004, because of their ongoing
support for various Operational Readiness Reviews. The Livermore Site Office Manager has informed
me that it is therefore necessary to move the completion date of the training
assessment to August 6, 2004.
Ms. Camille Yuan-Soo Hoo,
Manager, Livermore Site Office, is responsible for overseeing the training
assessment. Please feel free to contact
Ms. Yuan-Soo Hoo, or have your staff contact Ralph Kopenhaver at 925-422-3136
if you have any questions.
Sincerely,
Everet H. Beckner
Deputy Administrator
for Defense Programs