[DOE LETTERHEAD]
March 25, 2004
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities
Safety Board
625 Indiana Avenue, NW, Suite
700
Washington, D.C. 20004-2941
Dear Mr. Chairman:
In December 2003, I reported
completion of Commitment 4.2.1.5 in the Department’s Implementation Plan for
Software Quality Assurance (SQA) in response to Board Recommendation 2002-1. This commitment required the Department of
Energy (DOE) to conduct a survey of design codes currently in use to determine
if any should be included as part of the toolbox codes. The survey was completed and a copy of the design
code survey report was provided.
As part of our continuous
improvement effort, we have updated the design code survey report to include
additional survey data submitted by sites after completion of the first report.
Nineteen codes have now been identified
based on the additional survey results provided from other Departmental
organizations. However, as with the
first report, no additional codes were identified for inclusion in the DOE
toolbox based on this activity. The
additional design codes identified in the attached report are also proprietary
and/or are being maintained external to the Department. Some have also been through a formal software
quality assurance program. This activity
continues to help define the path forward for sharing design information,
notices, and upgrades on these key design codes.
Questions concerning the updated
Design Code Survey Report may be directed to Richard Lagdon at (301) 903-4218
or me at (301) 903-8008.
Sincerely,
Frank B. Russo
Deputy Assistant Secretary
Office of Corporate Performance
Assessment
Attachment
1.
Design Code Survey Final Report, Vol. 1
2.
Design Code Survey Final Report, Vol. 2
cc:
Beverly A. Cook, EH-1
Mark B. Whitaker, DR-1
Richard H. Lagdon, EH-31
Check C. Eng, EH-23