[DOE
LETTERHEAD]
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities Safety Board
Dear Mr. Chairman:
SUBJECT: Tailoring Department of Energy (DOE)
Requirements
At the public meeting you held in
While many people talk of tailoring DOE
requirements, the instances they cite do not actually involve changing the DOE
requirements. In most cases, the
perceived change in requirements is actually a matter of exercising the latitude
provided in the requirement on implementation.
For example, DOE O 5400.5, Radiation
Protection of the Public and the Environment, does not have a limit for the
release of volumetrically contaminated material. It requires that each methodology be approved
by the Office of Environment, Safety and Health (EH) on a case by case basis. So the alternate release criteria for the
Savannah River Operations Office, which was recently approved by EH, is the
result of using the latitude provided in the underlying requirements document.
One requirement that has been changed
relates to the DOE Radiological Control Manual (DOE/EH 056T). Originally issued in 1992, it was subsequently
cancelled by DOE N 441.1 in September 1995. In April 2002, the Savannah River Operations
Office approved a change to the WSRC Standards and Requirement Identification
Document, which deleted the manual. However, we maintained the requirement for
WSRC to document technical equivalency for any instance where they elect an
alternative approach to a “should” requirement contained in the Department’s
Radiological Control Standard (DOE-STD-1098-99).
While accelerating closure and completion of
the Office of Environmental Management’s mission will result in savings to the
taxpayers, I want to assure you that I will not compromise the safety of our
workers, the public or the environment for the sake of accelerated closure.
If you or your staff have
any questions, please feel free to contact me at 803-952-6337.
Sincerely,
Jeffrey M. Allison
Manager
GA-04-0040
cc: Jessie
Hill Roberson (EM-l), HQ
Paul Golan
(EM-2), HQ
Mark Whitaker
(DR-1), HQ
WSRC’s Additional Information for DNFSB Public Meeting on
December 4, 2003