[DOE
LETTERHEAD]
National Nuclear Security Administration
February 23, 2004
The Honorable John T. Conway
Chairman, Defense Nuclear Facilities Safety
Board
625 Indiana Ave, NW
Suite 700
Washington, DC 20004
Dear Chairman Conway
In your letter of March 31, 2003, you
requested to be informed of any delays in the schedule of several projects at
the Los Alamos National Laboratory. Among
them were the Partial Site-Wide Fire Alarm Replacement and the Waste Management
Risk Mitigation Projects. Both projects were
funded by Congress m Fiscal Year 2001 to mitigate the impact of the Cerro
Grande Fire and potential future damages from similar natural disasters.
The Performance Baseline of the Partial
Site-Wide Fire Alarm Replacement Project was scheduled for approval in July
2003, but was delayed in order to allow implementation of the recommendations
of an External Independent Review conducted by the Department of Energy Office
of Engineering and Construction Management. These recommendations have now been successfully
implemented and the project’s Performance Baseline was approved on January 22, 2004.
This approval authorized the project
team to commence procurement activities for the project. Starting this date, the project performance will
be measured and reported to the Department’s senior managers.
The Manager, Los Alamos Site Office, as the
delegated Acquisition Executive, approved the Waste Management Risk Mitigation
Project performance baseline in February 2003 with a 50 percent design hold
point, contingent upon completion of an approved Preliminary Documented Safety
Analysis. In July 2003, the Acquisition
Executive authorized the project team to complete the design. However, construction activities are still on
hold, pending approval of the Preliminary Safety Documentation that is under
review by the Los Alamos Site Office. As
a result, project completion could be delayed by approximately 11 months.
Our staffs are working with the Los Alamos
National Laboratory staff to expedite the review and approval of the Preliminary
Documented Safety Analysis. We will keep
you and your staff informed of any additional delays in the schedules.
Sincerely,
Linton F. Brooks
Administrator