[DNFSB LETTERHEAD]
August 26, 2004
Mr. Paul M. Golan
Acting Assistant Secretary for
Environmental Management
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0113
Dear Mr. Golan:
Enclosed is a report containing
observations of members of the staff of the Defense Nuclear Facilities Safety
Board (Board) concerning a review of the ongoing design and construction of the
electrical and instrumentation and control systems of the Waste Treatment Plant
(WTP) at the Hanford Site. These observations are based on a review of
available documents, as well as discussions with representatives of the
Department of Energy and contractor personnel at WTP on June 22-24, 2004.
The Board asks to be kept
abreast of the Department of Energy’s actions regarding the issues raised in
the enclosed report.
Sincerely,
John T. Conway
Chairman
c: Mr. Roy J. Schepens
Mr. Mark
B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff
Issue Report
August
3, 2004
MEMORANDUM FOR: J. K. Fortenberry, Technical Director
COPIES: Board Members
FROM: A. Gwal and R. Quirk
SUBJECT: Review of Electrical and
Instrumentation and Control Systems of the Waste Treatment Plant at the Hanford
Site
This report documents a review
by the staff of the Defense Nuclear Facilities Safety Board (Board) of the
electrical and instrumentation and control (I&C) systems of the Waste Treatment
Plant (WTP) at the Hanford Site. Staff
members A. Gwal
and R. Quirk met with on-site representatives of the Department of Energy’s
(DOE) Office of River Protection (ORP) and its contractor, Bechtel National,
Incorporated (BNI), on June 22-24, 2004, to discuss the status of issues
previously identified by the Board’s staff and to review the electrical and
I&C systems of WTP.
Background. Based
on earlier reviews of the 25 percent design, the Board issued a letter on March
7, 2003, concerning electrical and I&C systems planned for use at WTP. Since then, several actions have been taken by
DOE-ORP/BNI to close most of the issues identified in the Board’s letter. BNI estimated the design maturity for the
electrical systems to be approximately 50 percent at the time of June 2004
review.
Electrical
System. Overall the design of the
electrical system is progressing well.
However, several specific issues
related to this system, as well as open issues from previous staff reviews, are
detailed below.
Unprotected 13.8 kV Equipment at Substation A-6—During a facility walkdown of substation
A-6, the
Board’s staff observed that the equipment room containing 13.8 kV
switchgear does not
have an operational fire protection system. Although the building has sprinkler heads
installed, the system was intentionally disabled because of concern that the sprinkler
system water might enter the equipment that is vented at the top. Water spray from activation of the sprinkler
system would penetrate the equipment and could initiate water-induced short-circuiting, a common-cause failure that would leave
electrical loads without power. The
small portable fire extinguisher in the equipment room does not appear to
provide adequate fire protection, especially for a high fault-induced rapid
fire.
National Fire Protection
Association (NFPA) standard NFPA 13, Installation of Sprinkler Systems,
requires sprinkler
protection in electrical rooms. Institute of Electrical and Electronics Engineers
(IEEE) Standard 979, IEEE
Guide for
Substation Fire Protection, provides guidance related to fixed-pipe fire-extinguishing
systems that may be installed in substations. The standard states: “In unattended substations utilizing an
automatic system, consideration should be given to a system that automatically
shuts off when the fire is extinguished or after a predetermined time interval,
and then returns to the automatic operational mode.” The standard also cautions about the dangers
of water usage. It states that before
water is selected for use indoors, it should be determined whether the
equipment is watertight. Authorization
from the equipment manufacturer is also required. Additionally, the standard states: “If at all
possible, company personnel should de-energize the entire substation or, at a
minimum, the equipment involved in the fire, before the local fire department
is allowed on the site. This is recommended
because of the electrocution danger to the fire fighter by either direct
contact with energized equipment or indirectly with the water stream and hose
acting as a conductor.”
This issue could be resolved by
providing a raised noncombustible cover at the top, with concurrence from the
switchgear vendor, or through some other method that would prevent entry of
water into the switchgear instead of disabling the fire protection. The Pantex Plant recently addressed a similar
issue.
Medium-Voltage
Switchgear—The
4,160 V systems for four of the medium-voltage switchgears have no dedicated
ground fault protection for the feeder circuit to the motor starter, making it
unsafe to work near this system once it has been energized. The current design uses fuses (an old design
concept) that will need to be replaced each time a fault occurs. The use of fuses also makes it difficult to
coordinate the protective devices, which could result in the loss of the entire
bus during a fault. A design using
breakers could provide ground fault protection and permit coordination of
protective devices.
Manhole-47—During the facility walkdown, the
Board’s staff requested that manhole-47 (containing 13.8 kV
cables) be opened
to assess its condition. The staff
observed that concrete had poured through one of the openings in the duct bank
and deposited at the bottom of the manhole, partially covering the sump area. BNI staff present during the walkdown stated
they would correct this condition by carefully removing the concrete, and would
verify that this is not a problem in the other facility manholes.
Safety-Significant
Loads on
Safety-Class Busses—The staff noted that several
safety-significant loads are connected to the safety-class busses. IEEE Standard 384, Standard Criteria for
Independence of Class IE Equipment and Circuits, requires that non-safety-class
loads be appropriately isolated from safety-class busses to ensure that failure
of a safety-significant component would not cause failure of the safety-class
power system. Because of the large number
of connected safety-significant loads (18), it would be prudent to feed these
loads from dedicated safety-significant busses instead of using individual
isolation devices for each safety-significant load.
Safety
Requirements Document (SRD)—The
SRD for the electrical systems (Section 4.4-4) does not contain a complete list
of required standards as delineated in DOE Order
420.1, Facility Safety,
and DOE Guide 420.1-1, Nonreactor Nuclear Safety Design Criteria and Explosives
Safety Criteria Guide for Use with DOE Order 420.1, Facility Safety.
BNI engineers stated that they would revise the standards
list for Section 4.4-4 of the SRD.
Electrical Calculations—One-line drawings used for the
existing electrical calculations do not match the current one-line drawings. However, BNI has performed an informal
estimate of short-circuit and load-flow calculations and expects no major
issues in this area. The Board’s staff
will review the calculations once they have been completed.
Instrumentation
and Control Systems. As can be expected with a major
new design effort, the I&C design is significantly less mature than the
structural, mechanical, process, and electrical designs. Much of the I&C effort to date has focused
on requirements definition and development of software engineering processes
and procedures. The substantial software
engineering requirements, including significant documentation, implemented at
WTP appear to be appropriate for high-risk software.
Ventilation Control
System—The safety design class (SDC) C5
ventilation system is the key active system used to prevent exceedence
of site boundary radioactivity and hazardous chemical limits. One of the two independent C5 ventilation
trains will be in service during normal plant operations. The current design calls for starting the
standby train when total system exhaust flow falls below a nominal design value.
A conservative value of total system
flow can be used as a precursor for an imminent loss of system functionality. However, flow imbalances or
larger-than-anticipated inleakage into one C5 area
could result in meeting the total flow requirement concurrently with inadequate
vacuum in other C5 areas. The Board’s
staff suggested that monitoring the vacuum in each C5 room would be a more
appropriate control scheme for this SDC system. Additionally, the American Society of Heating,
Refrigerating, and Air-Conditioning Engineers Handbook Heating, Ventilating, and
Air Conditioning Systems and Applications suggests using static pressure
controls for ventilation systems in certain
manufacturing processes, clean rooms, and
laboratories. These examples are
analogous to the C5 ventilation system.
Safety Integrity Level
(SIL) Calculations—The principal industry standard adopted
for all safety instrumented systems in WTP is Instrumentation, Systems, and
Automation Society (ISA) 84.01, Application of Safety Instrumented Systems for the
Process Industries. For WTP,
the probability-based
SIL required by ISA 84.01 is developed using BNI’s Integrated Safety Management
process. BNI reported that the most
stringent requirement noted to date has been an SIL-2, which means the safety
system, including both hardware and software from sensors through final
actuation devices, can fail to operate as often as 1 in 100 attempted operations.
BNI will generate calculations
to demonstrate that the delivered systems are reliable enough to support the
required SIL. In these calculations, BNI
will assume that software developed by its staff will not result in a safety
system’s failure to operate. The Board’s
staff will review the reliability analyses for the safety instrumented systems
to better understand the technical basis for these positions.
Functional
Classification Transition—BNI
is in the process of reclassifying structures, systems, and components (SSCs). Instead of using the SDC/safety design
significant (SDS)/risk reduction class taxonomy, BNI will use DOE-STD-3009, Preparation Guide for U.S. Department
of Energy
Nonreactor Nuclear Facility Documented Safety Analyses, safety-class
(SC)/safety-significant (SS) taxonomy augmented by an additional protection
class (APC). It is expected that a
number of instruments will be reclassified from SDC to SS,
and others from SDS to APC. The Board’s
staff will review final design documentation to ensure that requirements such
as separation and isolation have been met for the reclassified SSCs.
Failure
to Invoke Single Failure—The
SRD, Section 4.3, addresses the seven criteria for engineered safety systems. Section 2.7.1 of Preliminary Safety Analysis Report (PSAR) to Support Construction
Authorization; General Information, Instrumentation and Control invokes the
appropriate SRD requirements for engineered safety systems except for criterion
4.3-2. Criterion 4.3-2 invokes consensus
standards for important-to-safety systems for which single-failure protection
is required. BNI engineers stated that
not including the single-failure criterion was an oversight; they also said
that the SDC/SC I&C systems will be protected from single failures. Although senior DOE staff stated that revising
the PSAR was not required because the SRD is an upper-tier document, BNI
engineers reported that they would initiate a change to the PSAR to
specifically invoke criterion 4.3-2 for SDC/SC I&C systems.