[DNFSB
LETTERHEAD]
August 6, 2004
The Honorable Linton Brooks
Administrator
National Nuclear Security
Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0701
Dear Ambassador Brooks:
The staff of the Defense Nuclear
Facilities Safety Board (Board) recently conducted a review of the analysis of
potential plutonium releases through leak areas in nuclear explosive cells at
the Pantex Plant. These cells were
specially designed to filter and entrap most of a radiological release when
exercised. The potential release of
plutonium would only occur in the extremely unlikely event of a high explosive
detonation that lacks the necessary explosive force to lift the cell roofs. A summary report of the Board’s review on cell
leak path areas is enclosed.
In September 2003, BWXT Pantex
declared a positive unreviewed safety question (USQ) as the result of the
discovery of incomplete welds in cell boundaries, allowing for larger-than-expected
cell leak areas. During subsequent
facility walkdowns, BWXT Pantex personnel found additional leak areas.
Since September, BWXT Pantex has
remeasured all the leak areas in each cell and recalculated the off-site dose
consequences. The current analysis for
the worst-case cell, considering leak area and plutonium loading, leads to an
off-site dose of 19 rem. While the analysis
incorporates many conservatisms, it takes credit for dispersal reductions that
are not adequately justified. The
analysis also includes dispersal reductions that result from repairs made to
address the incomplete welds. These
repairs may not be effective.
Without these reductions, the
potential off-site dose consequence from the worst-case cell during single-unit
operations will increase significantly, especially considering the significant amount
of uncertainty inherent in such calculations.
Therefore, pursuant to 42 U.S.C.
§ 2286b(d), the Board requests
that the National Nuclear Security Administration (NNSA) provide a briefing and
a report within 45 days of receipt of this letter on the status and path
forward of efforts to address the issues detailed in the enclosed issue report.
The Board requests that NNSA include in
its report a list, prioritized with respect to safety, of actions designed to
further mitigate potential off-site consequences in the event of a high
explosive detonation in a Pantex cell.
Sincerely,
John T. Conway
Chairman
c: Mr. Steven C. Erhart
Mr.
Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff
Issue Report
July
21, 2004
MEMORANDUM FOR: J. K. Fortenberry, Technical Director
COPIES: Board Members
FROM: C. Goff and C. Martin
SUBJECT: Cell Leak Path Areas and High
Explosive Accident Analysis at the Pantex Plant
This report documents a review
by the staff of the Defense Nuclear Facilities Safety Board (Board) of the
analysis of potential plutonium releases during an explosive event through leak
areas in nuclear explosive cells at the Pantex Plant. This review was conducted June 22-23, 2004, by
staff members C. Goff, D. Gutowski, T. Hunt, and C. Martin, and involved
briefings by BWXT Pantex personnel, calculation reviews, and walkdowns of
representative cells. A
follow-up
teleconference with Pantex Plant personnel was conducted July 7, 2004.
Background. The
cell leak area includes assumed-sheared piping plus cracks and gaps around
doors and penetrations that provide a pathway for plutonium to exit the cell in
the event of a high explosive (HE) detonation. The postulated accident of greatest concern is
a detonation of less than 70 pounds of HE, which does not produce the explosive
force necessary to lift the composite roof of the cell. When lifted, the specially designed graded
gravel overburden of the roof filters and entraps greater than 99 percent of
the plutonium involved in an explosive release. In the event the roof does not lift, pressure
created by the explosion is relieved by the air, containing plutonium aerosols,
exiting through the leak areas in the cell without benefit of any filtration.
In September 2003 it was
determined that the cell leak areas were larger than originally accounted for
in the Pantex safety basis. This
determination resulted in a positive unreviewed safety question (USQ)
determination. The sources of the larger
cell leak areas were insufficient welds around the equipment doors of some
cells. Instead of welding in a
continuous bead along the entire door and frame joint, 3-inch welds were made
every 6 inches, resulting in “stitch” welds. The unwelded areas contribute from 6 to 8 in2
of additional leak area per cell. These stitch
welds were first discovered in 1997, and a work order was generated but never
completed. Nuclear explosive operations
in the cells were terminated in September 2003 after it was discovered that the
work order was still open after 6 years. A commercial sealant was procured and used to
seal the stitch-welded joints, and explosive operations were resumed. BWXT personnel explained that the joints had
not been welded because of concerns regarding door deformation upon exposure to
the high temperatures of welding.
Since September, BWXT has
remeasured all of the leak areas in each cell and recalculated the off-site
dose consequences. The newly calculated
leak areas are more than triple the areas originally reported: 160 in2 as compared with 42 in2
for the cell with the largest leak path. As part of the task to reverify the leak
areas, the contractor estimated the cost of further reducing the leak areas to
be $15-20 million.
Cell Gap Analysis. Sandia
National Laboratories (SNL) performed cell leak area dispersal calculations in
1996 to support the preparation of a Justification for Continued Operation
(JCO) for the Pantex cells. In the
calculations, a factor of 2 reduction in the plutonium release fraction was
taken because of inertial deposition of the particles at knife-edge interfaces,
such as under equipment doors. Depending
on the cell, knife-edge interfaces can account for up to 54 percent of the cell
leak area. This reduction was taken based
on a 1996 computational analysis performed by Battelle Memorial Institute (BMI)
using the COMPACT-2D computer code. The
analysis was validated by a “back-of-the-envelope” calculation that appears to
have ignored important physical considerations, such as surface roughness,
sticking coefficients, and the effects of moisture and temperature on these
variables. A factor of 3 reduction was
suggested by the BMI calculation, but SNL preferred a more conservative approach
and chose to take a factor of 2 reduction. The Board’s staff reviewed BMI’s calculations
and concluded that the computer analysis is not sufficiently compelling to
justify any knife-edge reduction.
BWXT has assumed responsibility
for the off-site consequence calculations, and is using a calculation
methodology similar to that employed by SNL. The most recent calculation (Calculation 3079,
Revision 4, Addendum 4) incorporates the larger leak areas and uses
unit-specific amounts of HE and plutonium. The BWXT calculations do incorporate a number
of conservatisms, including the assumption that all plutonium transported
through the leak areas is considered part of the plume source term. This assumption is conservative because it
takes no credit for hold-up in the ramps outside the cell. However, the calculation also includes the BMI
knife-edge reduction, taking credit for a factor of 3 reduction in plutonium
aerosols. BWXT personnel were unable to
provide further justification for allowing the reduction beyond giving the
Board’s staff BMI’s summary report.
Sealant Procurement. The
Board’s staff reviewed the procurement process for the commercial sealant used
to supplement the stitch welds in the cells. The sealant, Rebond 907 Gasket Former from
Cotronics Corporation, was identified as a Class 1 (safety-class) component,
but procured as a commercial-grade item without a commercial-grade dedication process.
No confirmatory testing was performed on
the sealant, and the procurement document lists no required specifications,
such as temperature and pressure ratings.
During a walkdown of one of the
cells, the Board’s staff observed that the sealant used to patch unwelded
joints was peeling and detaching from the door structure. The manufacturer’s installation instructions
for the sealant required application onto clean steel surfaces, but the door frame
had only been wire-brushed, not stripped of paint, before application. BWXT personnel noted that a maintenance order
had been filed to reapply sealant to the gap. They were not particularly concerned about the
detaching sealant because, as they explained, the sealant on the outside of the
door frame is not credited with sealing the stitch welds. Because of the placement of a door gasket,
however, the credited sealant on the inside of the door frame was inaccessible for
inspection. The peeling and detaching of
the external sealant raises concern as to the ability of the sealant to perform
its intended safety-class function on the inside joints of the doors.
Dose Consequences. The
worst-case off-site dose consequence was reported (in Calculation 3079) to be
19 rem for single-unit operations in a cell. This estimate includes the factor of 3
reduction on knife-edge gaps and the repairs recently made to the cells using
the commercial sealant. Without these
reductions, the off-site dose consequence from the worst-case cell during
single-unit operations could challenge the site boundary evaluation guideline
of 25 rem, especially considering the significant amount of uncertainty
inherent in dose modeling. The results
of a calculation for two-unit operations yielded a 43.2 rem dose at the site
boundary. Multi-unit operations are not
currently authorized, but are being considered.
Conclusions. In
light of the postulated dose consequences, improvements need to be examined and
prioritized with respect to minimizing cell leak areas. In addition, while inertial deposition along
knife-edge interfaces in the cell almost certainly occurs to some degree,
credit for this effect ought to be limited to that which can be demonstrated in
a compelling technical argument, through either a more rigorous calculation or
benchmark experiments demonstrating deposition. In the same vein, the commercial sealant used
to repair the stitch weld gaps should not be credited with reducing the leak
path until it has been adequately tested to ensure that it will fulfill its
required safety-class function. It would be advisable to investigate other
stitch weld repair options, such as low-temperature welding.