[DNFSB
LETTERHEAD]
December 13, 2004
Mr. Paul M. Golan
Acting Assistant Secretary for
Environmental Management
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0113
Dear Mr. Golan:
The Defense Nuclear Facilities
Safety Board (Board) has been reviewing the performance of activity-level work
planning and work control at defense nuclear sites for several years. The Savannah River Site (SRS) has
traditionally implemented an Integrated Safety Management System at the
activity-level that has resulted in an adequate work planning and work control
system. However, recent changes in the
hazard analysis process, as well as the increased risk associated with
deactivation and decommissioning efforts, have resulted in a number of notable occurrences
in which workers received unplanned exposures or contamination was released. Corrective action is necessary to preclude
further degradations in performance.
The Board notes that the
site-wide work planning and control program and its directives are being
modified and improved as the deactivation and decommissioning processes mature. During a recent visit to SRS, however, the
Board's staff observed that sets of controls are often developed to work scopes
covering several weeks or months of work. As a result, the identification and analysis
of specific or unique hazards associated with the actual daily or weekly work
and the requisite development of appropriate controls may be inadequate. The use of standard and broad scope type work
packages are generally employed in an attempt to increase productivity. However, experience has shown that this
practice can lead to safety problems, as was the case last year with the
glovebox fire at the Rocky Flats Environmental Technology Site. More frequent identification of specific
emerging hazards is particularly important in evolving activities such as
deactivation and decommissioning. This
concern is heightened for the more complex deactivation and decommissioning
activities that will be carried out at SRS in the future.
Subsequent to the staffs visit,
the Department of Energy’s Savannah River Operations Office issued a letter to
Westinghouse Savannah River Company (WSRC) identifying the problem with WSRC’s
process for conducting hazard identification. Furthermore, during the Board’s visit to SRS
on November 17, 2004, the site discussed specific actions being taken to address
these concerns. To assist you in making
improvements to the work planning process, a report documenting the results of
the staffs review at SRS is enclosed for your information and use.
Sincerely,
John T. Conway
Chairman
c: Mr. Jeffrey M. Allison
Mr.
Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff
Issue Report
November
2, 2004
MEMORANDUM FOR: J. K. Fortenberry, Technical Director
COPIES: Board Members
FROM: D. Burnfield
SUBJECT: Activity-Level Work Planning and
Control of Deactivation and Decommissioning Work at the Savannah River Site
This report documents a
programmatic review of work planning and control for deactivation and
decommissioning (D&D) activities at the Savannah River Site (SRS). This review was conducted by members of the
staff of the Defense Nuclear Facilities Safety Board (Board) D. Burnfield, D.
Owen, and J. Contardi, assisted by outside expert D. Volgenau. The focus of the review was on how the
Integrated Safety Management (ISM) process is used to identify and implement
appropriate controls to protect workers from activity-level hazards. The review concentrated on D&D work
activities at F-Area Complex. To
demonstrate the methods used for activity-level work planning, site personnel
chose the 247-F facility, a large facility with many hazards, both chemical and
radiological (e.g., gloveboxes, process piping).
Background. SRS
is in the early stages of a new and difficult long-term D&D activity.
The current contract covers
fiscal years (FY) 2003 to 2006, but site D&D is expected to continue for
many years beyond the current contract. In October 2003, the site contractor,
Westinghouse Savannah River Company (WSRC) integrated another contractor, CH2
Savannah River Company (CH2SRC), into the site D&D effort and reorganized
the effort under a single manager. CH2SRC brought in a group of 15 managers from
the Rocky Flats Environmental Technology Site who also had commercial D&D
work experience.
The D&D work at SRS is
planned and performed essentially within the site’s existing ISM System. Because of the unique challenges and
requirements of D&D work, WSRC had developed a specific program and
associated directives for planning and accomplishing such activities. Through a formal process, the 247-F facility
had been isolated electrically and mechanically from external sources of
energy, and temporary services (e.g., lighting, portable air conditioning, fire
alarms) had been installed in the facility to facilitate work.
The D&D work planning and
control program and associated site directives are being modified and improved
as the processes mature. Although there
are provisions for the use of subcontractors in the site D&D contract, a
decision was made in January 2004, for various reasons, to commence converting
all D&D work to in-house (WSRC) assets. This conversion had nearly been completed at
the time of the staffs review, though it was expected to take until the end of
FY 2006 to finish redirecting all subcontractor work out of the D&D arena.
Observations. To
safely accomplish the large amount of unique D&D work expected in the near
term, SRS must improve its work planning and control processes to account for
the difficulty and uniqueness of D&D work. The following observations, organized
according to the five core functions of ISM, support this conclusion.
Define the
Scope
of Work—At the time of the staffs
review, D&D work was clearly defined, prioritized, organized, and planned
only at the top level. A site D&D
work control procedure had been issued that directed how D&D work was to be
defined and planned. This procedure
provided for the unique requirements of D&D work while referencing
established site procedures where appropriate. D&D projects for a given facility were
typically subdivided into smaller work areas called “zones.” For the 247-F facility there were 100 zones,
82 of which involved a radiological or chemical hazard. Each zone was assigned to a planning team that
consisted of an engineer, a planner, subject matter experts (SMEs), a
first-line manager, and a team of D&D technicians. Their efforts were overseen by a D&D
manager and a project manager. The
top-level work to be accomplished in the overall zone was used as the main task
for each zone work planning effort. Up
to several unique subordinate tasks were included for any given zone.
As a first step in the work
planning process, an engineer typically completed a characterization of the
zone’s environment—including
identifying potential hazards—in
which the main and subordinate work tasks were to be conducted. Using this information and other data (e.g.,
from extensive team walkdowns, radiological surveys, and discussions with the engineer
and SMEs), a planner then executed an automated hazard analysis (AHA) and constructed
a draft work package for review by the balance of the work planning team.
The result of this process was a
large work package for all of the work to be accomplished during the next 3-4
months in that zone. Typically, the
package contained the engineer’s characterization report, two AHAs (one for the
main task and another for the subordinate tasks), top-level work instructions,
two standing radiological work permits (RWP) (one for low-risk work and another
for higher-risk work), and various other attachments. The package was then approved by the project
manager, the D&D manager, and the first-line manager before it was issued.
Although the work planning
process included many sound practices, the resulting work package did not
define and plan the work that was actually to be done on a daily or weekly
basis. Decisions on what specific work
to perform daily or weekly were to be made by the first-line manager, who was
responsible for identifying and using those portions of the work package pertinent
to the work to be conducted. No
systematic tools were provided to the first-line manager for accomplishing this
task. The result has been variability in
the quality of the work performed and in the ability to control the work to
maximize the safety of the workforce.
Analyze
the Hazards—The
AHA process is used to assist in identifying hazards and appropriate controls
for planned work. This process replaced
a manual system in October 2003. As
noted above, the
work planner used the AHA tool
to identify the hazards (and the resulting controls) for the main and
subordinate tasks in the work package. The result was then discussed, along with the
draft work package, during a work team AHA meeting. This meeting resulted in a final work package.
Since the work had been defined only at
the top level, the specific hazards to be encountered during daily or weekly
work were not identified and analyzed. The AHA tool could not readily be tailored for
the identification and analysis of specific or unique hazards associated with a
particular zone. Radiological hazards
were not analyzed in the AHA; instead, reference was made to the RWPs contained
in the work package. The RWPs were not
specific to task and zone work. Some
D&D managers believed that the AHA process in its present form, complicated
their work planning efforts, and that the system was not responsive to the incorporation
of changes designed to enhance the identification and analysis of D&D work hazards.
Many of the weaknesses of the AHA
process also would be a problem in work planning efforts for areas other than
D&D at SRS.
Develop
and Implement Controls—Although
the work procedures reviewed by the staff had adequate controls for the
identified hazards, the lack of an adequate process to identify and plan for
the actual work being done on a daily or weekly basis, coupled with the
weaknesses identified in the AHA process, made it impossible to conclude that
the appropriate work controls had actually been implemented. The AHA tool simply dictated specific work
controls for a potential hazard and did not foster a hazard analysis that would
have resulted in implementation of the hierarchy of controls identified in
Department of Energy (DOE) Order 440.1A, Worker
Protection Management for DOE Federal and Contractor Employees. Further, there was no process for identifying
and resolving potential conflicts between the mandated work controls.
Perform
Work—Despite
the above-noted weaknesses in the D&D work planning process and several
D&D-related occurrences documented in recent months, it appeared that the
D&D work was being accomplished with a high level of concern for worker
safety. First-line managers were
observed giving thorough pre-job/task briefings, with worker participation. However, it did not appear that zone work
packages were always being closed out in a timely manner. Managers appeared to be experienced and
responsive, and demonstrated a highly positive attitude regarding the projects
in which they were engaged. Managers and
members of the work planning team were noted to be in the field observing work
on a frequent basis. An aggressive
training program for managers and workers, designed to support safety in
D&D work, was in progress and maturing; plans were being made to
institutionalize recent changes to correct deficiencies.
Provide
Feedback and Continuous Improvement—The site contractor had prescribed a number of processes for
self-assessment and the capture of lessons learned for continuous improvement. The effectiveness and maturity of these
processes varied. Lessons learned from D&D
activities at other sites, as well as SRS D&D work, could be captured more
effectively. An impediment to this was
the apparent lack of post-job reviews and timely closeouts of work packages. Some efforts did appear to be effective. For example, (1) reviews and critiques of occurrences
appeared to be thorough, with lessons learned being captured and promulgated;
(2) a Behavior-based Safety System of workers observing workers during work had
recently been initiated and appeared to be maturing and providing some useful
feedback; (3) the presence of managers and supervisors in the field had
resulted in immediate corrective action in several cases; and (4) a proactive report on work
planning issues resulting from the 2003 Rocky Flats glovebox fire had been
provided to the workforce.
DOE Contractor
Oversight—DOE’s
Savannah River Operations Office (DOE-SR) appeared to be overseeing D&D
work effectively. The Closure Project
Office was using project teams consisting of D&D project leads and facility
representatives who were supported in a matrix manner by SMEs. The facility representatives appeared to be
well qualified, while the project leads were undergoing training and
qualification. Many of the individuals
had significant DOE or other related experience. The project leads and facility representatives
were attending daily and periodic contractor meetings, were actively providing
feedback to the contractor, and were validating the contractor’s corrective
actions and milestone completions. The
facility representatives were spending considerable time in the field observing
work. DOE-SR has also conducted some
annual contractor assessments. However,
additional training may be necessary to ensure that DOE-SR personnel understand
the fundamental aspects of a good process for activity-level work planning and
control so they can establish appropriate expectations for the contractor’s
processes.
Conclusion. The
site has a large future D&D workload, which will involve much more complex
and hazardous activities. It is critical
that SRS develop solid processes and procedures for this new and different type
of work. These processes and procedures
must reflect the differences between D&D activities and current site work
and be written to alleviate the burdens currently placed on the first-line
manager.