The purpose of this letter is to report on
the status of commitment 4.4.7 in the Implementation Plan for the Defense
Nuclear Facility Safety Board Recommendation 98-2, “Accelerating Safety Management
Improvements at the Pantex Plant.”
The commitment 4.4.7 requires the delivery
and implementation of accelerated critical tooling for the W78 and. W88 weapon
programs. Critical tooling for the W78
has been incorporated into the W78 and is undergoing readiness reviews and a
Nuclear Explosive Safety Study for approved use. For the W88, the National Nuclear Security Administration
approved the Nuclear Explosive Safety Study on
If you have further questions, please call
Mr. Marty Schoenbauer on 202-586-1730.
Sincerely,
David E. Beck
Assistant Deputy Administrator
for Military Application and
Stockpile Operations