[DOE
LETTERHEAD]
January
17, 2003
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities
Safety Board
625 Indiana Avenue, NW, Suite
700
Washington, D.C. 20004-2901
Dear Mr. Chairman:
Reference: Defense Nuclear Facilities Safety Board
letter from J. T. Conway to J. H. Roberson, DOE, dated November 4, 2002.
This letter provides the U.S.
Department of Energy (DOE) report in response to deficiencies in safety basis
development identified by Defense Nuclear Facilities Safety Board (DNFSB) staff in
the period April 30 through August 2, 2002, and reported to DOE on November 4,
2002, in the Reference. The Reference
identified three summary level concerns and enclosed two Staff Issue Reports
with amplifying details of those concerns.
This letter addresses the summary level concerns. Enclosure 1 provides the detailed response
to all of the concerns. The DOE has
concurrently performed a rigorous review and inspection of the contractor’s
safety basis development, including these issues, beginning in November 2001
and continuing. Enclosure 2 summarizes
the relevant portions of this effort.
The DOE strongly agrees that a
rigorous Integrated Safety Management (ISM) review is important, and that some
(safety) conditions were not adequately addressed in the Preliminary Safety
Analysis Report (PSAR). The formal
safety review performed by the DOE Office of River Protection (ORP) is the most
rigorous of any performed to date by DOE on a new Hazard Category 2 facility at
the preliminary design stage and is documented in over 1,200 detailed questions
and responses, previously provided to the DNFSB staff. The ORP employed 63 contract specialist
engineers (approximately 22 FTE) and inspectors, and six full time Federal staff. Their qualifications and experience are
summarized in Enclosure 4. DOE
considers that, due to the extensive commitments obtained through the formal
safety review process (summarized in Enclosure 3), the deficiencies in the ISM
review were remedied sufficiently to authorize construction in carefully
controlled increments. These increments
began August 16, 2001, and have continued in two subsequent
authorizations. (The two final
incremental construction authorizations are anticipated in late January 2003
(pretreatment) and September 2003 (analytical laboratory).
Of course, DOE will continue to
employ a vigorous inspection and assessment program of the contractor to ensure
that, as the design evolves, ISM reviews focus on and resolve key outstanding
design safety concerns. The DOE agrees
that additional controls or design modifications may be necessary before
adequate levels of safety are achieved and expects the contractor to determine
whether any are necessary in subsequent ISM reviews that are currently
underway. The DOE will continue to ensure
that the resulting final designs are both cost effective and achieve adequate
safety.
With respect to the observation
that design calculations and inputs were deficient, DOE has considered this a
serious weakness, and has aggressively questioned and assessed the contractor’s
performance and corrective actions.
Enclosure 2 references related DOE reviews in this area. The DOE will ensure that the contractor’s
corrective actions are effective by follow-up assessments and inspections in
the next year. The first of these
assessments is currently scheduled for January 2003, prior to full construction
authorization of the Waste Treatment and Immobilization Pretreatment facility
on the Hanford Site.
With respect to the observation
that the contractor treated the DOE’s accident evaluation guidelines as fixed
criteria for determining the acceptability of the design DOE considers that the
contractor presentations to the DNFSB staff did not adequately explain that the
guidelines are only one of a suite of considerations used to determine the
acceptability of the design, and are not fixed acceptability criteria. Enclosure1 attempts to further clarify this
important point. Throughout its review
of the PSARs, DOE has insisted that the contractor ensure that the unmitigated
consequences of accidents are the primary determinant of control strategies for
those accidents, consistent with the guidelines in DOE STD-3009-94, Appendix
A. The DOE will reassess the
contractor’s performance in the closeout review of related authorization
agreement conditions of acceptance and in inspections of further contractor
hazard analysis that are occurring as the design matures.
Thank you for the assessment of
this vitally important area. If you
have further questions, please contact me at (202) 586-7709.
Sincerely,
Jessie Hill Roberson
Assistant Secretary
for Environmental Management
Enclosures:
3. CAR Conditions
of Acceptance
cc w/enclosures:
B. A. Fiscus, RL
D. J. Grover, DNFSB Hanford Site
Rep.
R. J. Schepens, ORP
Schneider, EM-44
M. B. Whitaker, S-3.1