UCNI
[DOE LETTERHEAD]
April 24, 2003
The Honorable John T. Conway
Chairman
Defense Nuclear Facilities Safety Board
625 Indiana Avenue, NW.
Suite 700
Washington, D.C. 20004
Dear Mr. Chairman:
Enclosed is the quarterly report for your
Recommendation 98-2 for the period January 1 through March 31, 2003.
During this reporting period, the Department
made progress toward completion of all commitments, and completed Commitment
4.3.2, Readiness Assessment Report for Fire Protection (Enclosure 4). The Pantex contractor also took delivery of
the prototype tooling for W88 bay operations and W78 bay and cell operations in
partial fulfillment of Commitment 4.4.7, Accelerated Tooling. Twenty out of twenty-eight commitments have
been delivered, and eight remain outstanding.
I propose incorporating the quarterly brief
into the agenda for Board’s next regular visit to the Pantex Site or
incorporating the status of open commitments into the agenda items where they
naturally arise, at the Board’s discretion.
The viewgraphs customarily used to report the status of open commitments
are enclosed.
If you have any questions, please contact me
or have your staff contact Jeff Underwood 301-903-8303.
Sincerely,
David E. Beck
for Military Application and
Stockpile Operations
Defense Programs
4 Enclosures
Matter transmitted contains UCNI.
When separated from enclosures, this
cc w/enclosures:
J. McConnell, DNFSB
W. Andrews, DNFSB
A. Matteucci, DNFSB
M. Whitaker, S-3.1, HQ
D. Glenn, PXSO
Matter transmitted contains UCNI.
When separated from enclosures, this
Documents is not UCNI