[DNFSB LETTERHEAD]
June 12, 2003
The Honorable Spencer Abraham
Secretary of Energy
1000 Independence Avenue, SW
Washington, DC 20585-1000
Dear Secretary Abraham:
On March 8, 2000, the Defense Nuclear
Facilities Safety Board (Board) issued Recommendation 2000-2, Configuration
Management, Vital Safety Systems.
This recommendation called for the Department of Energy (DOE) to take
steps to ensure that safety systems for defense nuclear facilities will remain
reliable and effective. In particular,
the Board stressed the actions required to ensure the reliability of
confinement ventilation systems. The
Board approved DOE’s Implementation Plan for Recommendation 2000-2 on December
14, 2000. This plan consists of 29
specific actions designed to meet the intent of the recommendation. Two of the key actions required by the plan
are the performance of initial reviews of vital safety systems (Phase I
assessments), followed by more detailed reviews of selected vital safety
systems (Phase II assessments).
The Board’s staff observed several Phase II
assessments and reviewed the reports on all completed assessments, as well as
the implementation of the requirements for providing qualified federal and
contractor employees cognizant of the vital safety systems. A report summarizing these reviews is
enclosed for your use in assessing the progress at several DOE sites.
The Board is particularly interested in
DOE’s efforts to institutionalize these assessments. In a letter dated April 7, 2003, the National Nuclear Security
Administration (NNSA) provided a discussion of the processes the NNSA sites are
using to institutionalize the Phase II assessments and stated that NNSA
expected each site office manager to appraise the implementation of these
processes. The Office of Environmental
Management provided the Board with a similar discussion in a letter dated May
2, 2003. In this letter it was noted
that institutionalizing these assessments would not be completed at the Rocky
Flats Environmental Technology Site (RFETS).
This is acceptable for RFETS; however, a systematic study should be
completed before curtailing similar assessments at other closure sites.
The Board has directed its staff to continue
to work with DOE on resolving the remaining issues associated with the implementation
of Recommendation 2000-2 identified in the Board’s letter of September l8,
2002. Specific items that remain to be
completed include:
The Board considers that implementation of
Recommendation 2000-2 should result in improved configuration management and
reliability of vital safety systems at defense nuclear facilities. Further, the Board believes that both DOE
and NNSA must vigorously pursue the completion of this important activity. Therefore, pursuant to 42 U.S.C. § 2286b(d), the Board requests to be briefed
within 6 months of receipt of this letter on the status of the following: (1) site activities to institutionalize the
Phase II assessments, (2) the staffing of federal and contractor subject matter
expert/systems engineer positions, (3) changes to DOE’s engineering-related
functional area qualification standards, (4) issuance of the revised Nuclear
Air Cleaning Handbook, and (5) actions being taken to address the common
weaknesses and lessons learned identified in the enclosed report.
Sincerely,
John T. Conway
Chairman
c:
The Honorable Linton Brooks
The Honorable Robert Gordon Card
The Honorable Everet H. Beckner
The Honorable Beverly Ann Cook
The Honorable Jessie Hill Roberson
Mr. Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff Issue Report
April 24,
2003
MEMORANDUM FOR: J. K.
Fortenberry, Technical Director
COPIES: Board Members
FROM: D. L. Burnfield
SUBJECT: Summary of Site Visits to Review Progress in
Implementing Recommendation 2000-2, Configuration Management, Vital Safety
Systems
This report documents observations resulting
from visits made to four sites in the Department of Energy’s (DOE) weapons
complex by members of the staff of the Defense Nuclear Facilities Safety Board
(Board). The purpose of these visits
was to evaluate progress made in implementing the Board’s Recommendation
2000-2, Configuration Management, Vital Safety Systems. Reviews were conducted at the Y-12 National
Security Complex (Y-12), the Pantex Plant, the Hanford Site (Fluor Hanford,
CH2M Hill, and Pacific Northwest National Laboratory), and Lawrence Liver-more
National Laboratory (LLNL). The visits,
led by D. Burnfield with J. DeLoach and outside expert D. Volgenau, were
conducted during a 6-month period from July 2002 to January 2003, with follow-up
discussions and documentation reviews being performed through March 2003.
Background. The
Implementation Plan for Recommendation 2000-2 includes commitments to improve
the competence of DOE and contractor engineering personnel, as well as to
perform summary (Phase I) and detailed (Phase II) assessments of the material
condition and operability of vital safety systems, including the programs that
support them (e.g., maintenance and engineering). The reviews at the five DOE site offices (two at Hanford)
emphasized these commitments. Specific
areas evaluated included the following:
(1) DOE’s subject matter expert (SME)/systems engineer programs; (2)
Site contractor systems engineering programs; and (3) Phase II assessments,
which included a walkdown by the staff of one or more vital safety systems at
each site.
Summary. Although it appeared that, for
the four sites visited, the managers of the DOE site offices and of the site
contractors were actively supporting the intent of Recommendation 2000-2 and
were working to implement its principles, there was a wide disparity in the
effectiveness of their actions:
Detailed Observations. The
following observations support the above summary comments.
DOE’s SME/Systems Engineer Programs―As noted, this area remains weak at all of
the site offices visited, and the intended benefits in terms of contractor
oversight remain to be fully realized.
All of the DOE site offices had established SME/system engineer
organizations; however, a program had been developed, recently promulgated, and
implemented only at the Y-12 and LLNL site offices. The Pantex Site Office (PXSO), DOE-Richland Operations Office
(DOE-RL), and the Office of River Protection had yet to fully establish
effective SME/systems engineer programs.
Common weaknesses noted in the existing programs included the following:
Contractors’ Systems Engineering Programs―As noted, the Board’s staff observed a wide
disparity in the effectiveness of the site contractors’ systems engineering
programs. Both BWXT at Y-12 and CH2M
Hill at the Hanford tank farms had implemented well-founded and robust systems
engineering programs. These programs
are maturing. The contractors appeared
to be cognizant of the areas requiring further emphasis and enhancement and
were working aggressively to improve their programs and to increase the
staffing to allow adequate coverage of all vital safety systems. The programs at the remaining sites suffered
from a number of shortcomings and were much less effective; several required
increased staffing. Each could benefit
from the lessons learned at Y-12 and the Hanford tank farms. The staff observed that the contractors for
the other Hanford Site projects and the environmental management facilities at
LLNL had particularly weak systems engineer programs. The following are examples of common weaknesses noted in these
contractors’ systems engineer programs:
The two contractors with strong systems
engineer programs demonstrated some common strengths, such as the following:
The best of the material assessments
included specific requirements to note conditions, ensure that deficiencies
were corrected, and trend important parameters to identify degradation.
Phase II Assessments―Each of the visited sites has scheduled or
completed its Phase II assessments. All
of the site contractors believed they were making progress toward
institutionalizing the principles of Recommendation 2000-2; however, some were
found to be doing better than others in this regard. The contractors for Y-12 and the Hanford tank farms had been the
most aggressive in accepting and working to correct the areas for improvement
noted in the Phase II assessments. None
of the sites had fully institutionalized a process for conducting Phase II-like
assessments. The contractors for some
of the sites, such as Hanford, were examining how such a process might be
incorporated into existing assessment processes. Other sites, such as LLNL, had not yet given this area much
consideration.
The Board’s staff reviewed system drawings
and then conducted a walkdown of one or more vital safety systems together with
representatives of DOE and the contractors during each of the site visits. In general, both the federal and contractor
systems engineers demonstrated good knowledge of their systems, and each
system’s material condition appeared to indicate that it was being maintained
adequately. A common weakness noted was
a lack of understanding on the part of systems engineers of how to properly
assess the material condition of their system(s).
A review of the Phase II assessments
completed at Y-12 and subsequent discussions with site personnel revealed some
lessons learned that ought to be considered for applicability across the DOE
weapons complex: