[DNFSB LETTERHEAD]
March 7, 2003
The Honorable Jessie Hill Roberson
Assistant Secretary for Environmental
Management
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0113
Dear Ms. Roberson:
Enclosed is a report detailing observations
made by members of the staff of the Defense Nuclear Facilities Safety Board
(Board) concerning electrical distribution and instrumentation and control
systems being designed for the Hanford Site’s Waste Treatment Plant. These observations were developed through
document reviews and discussions with representatives of the Office of River
Protection and Bechtel National, Incorporated.
At this early stage, the Board believes the overall design philosophy
being employed with respect to these systems is sound. Several specific areas were noted, however,
that may warrant increased attention as the design progresses. These areas are discussed in the enclosed
report, which is forwarded for your information and use, as appropriate.
Sincerely,
John T. Conway
Chairman
c:
Mr. Roy J. Schepens
Mr. Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff Issue Report
January 21,
2003
MEMORANDUM FOR: J.
K. Fortenberry, Technical Director
COPIES: Board
Members
FROM: B.
Broderick, R. Quirk
SUBJECT: Electrical
Distribution and Instrumentation and Control Systems, Hanford’s Waste Treatment
Plant
This report documents a review by the staff
of the Defense Nuclear Facilities Safety Board (Board) of the design of
electrical distribution and instrumentation and control (I&C) systems for
the Waste Treatment Plant (WTP) at the Hanford Site. Members of the Board’s staff B. Broderick, A. Gwal, S. Stokes,
and R. Quirk assessed the design with the participation of on-site
representatives of the Department of Energy’s (DOE) Office of River Protection
(ORP) and its contractor, Bechtel National, Incorporated (BNI).
Background.
Large-scale construction for the WTP project has recently begun. However, the portions of the design
pertaining to important-to-safety (ITS) electrical distribution and I&C
systems are still being developed. BNI
has estimated the design maturity for these systems at approximately 25
percent.
Although they have not been formally
approved by DOE, there are two major design amendments proposed by BNI for the
WTP project that would significantly alter the configuration and demands on ITS
electrical systems. The first potential
modification would alter the number of production melters from three in the
Low-Activity Waste (LAW) Facility and one in the High-Level Waste (HLW)
Facility, to a two and two configuration.
Given the reliance on emergency power and I&C systems to operate and
actuate hazard controls that would prevent or mitigate postulated melter
accidents, changes in the quantity or location of the melters will require
associated design changes to ITS electrical systems. The other potential change would reduce the number of redundant
emergency load trains and, by extension, the number of emergency diesel
generators, from three to two. There is
currently no reason to believe that these design changes will adversely impact
safety, however, if implemented, they will require vigilance on the part of
both BNI and ORP to ensure that associated design changes are thoughtfully and
effectively realized in this fast-paced project.
Electrical Distribution Systems. At
this stage of design, it appears that the design philosophy being applied to
the normal and emergency power distribution systems is sound. Several specific areas were noted, however,
that may warrant increased attention as the design progresses. These areas are detailed below.
Functional Classification of Support Systems―The staff noted an example of a
safety-design-class (SDC) ITS system being supported by equipment whose
functional classification is currently listed as general service. In the HLW and LAW facilities, the ambient
thermal environment in which SDC uninterruptible power supply (UPS) systems
operate is controlled by non-ITS heating, ventilation, and cooling (HVAC)
systems. If the non-ITS HVAC systems
were to fail, temperature conditions in the UPS rooms could drift outside the
ranges specified for proper operation, potentially rendering the UPS systems
incapable of performing their credited safety functions. BNI personnel had identified this potential
deficiency independent of input from the Board’s staff, and are currently
evaluating a functional reclassification of the HVAC systems planned for use in
the HLW and LAW UPS rooms.
Identification of Risk-Reduction―Class Structure, Systems, and Components-The
Safety Requirements Document (SRD), in Section 1.0-8, establishes a unique
classification of Structures, Systems and Components (SSC) called Risk
Reduction Class (RRC). These RRC SSCs
are defined as those SSCs which are ITS but do not meet the criteria that would
necessitate an SDC or safety-design significant (SDS) designation. The Board’s staff identified two SSCs-the
lightning protection system and standby diesel generators-that are currently
categorized as non-ITS despite performing functions that appear to fit the SRD
definition of RRC.
The uncontrolled propagation of lightning
energy through structures can adversely impact safety in a variety of
ways. Lightning-induced voltage surges
can damage unprotected equipment, and even surge-suppressed systems can be
rendered unavailable by overvoltage tripping.
Uncontrolled lightning energy also serves as an initiating event for
fires and explosive arcing and can pose serious electrical hazards to
workers. Lightning protection systems
provide convenient attachment points for lightning strikes and a low-impedance
path to ground that guides lightning current away from the building
interior. By providing a means for
controlling the energy (including its path and dissipation media) associated
with a lightning strike, an effectively installed and maintained lightning
protection system can reduce challenges to SDC and SDS SSCs, in addition to
reducing or eliminating fire and electrical hazards associated with lightning. Consequently, it appears that the function
of the lightning protection system is appropriate for RRC classification.
The offgas system for the LAW melter is an
SDC SSC credited for maintaining a continuous flow path from the melter to the
exhaust stack. This system prevents
exposure of facility workers to oxides of nitrogen generated during the
vitrification process. Should a loss of
offsite power occur, each of the melter offgas exhausters is backed up by an
SDC UPS unit with the capacity to power the equipment for only a finite amount
of time. While this arrangement appears
adequate, the Preliminary Safety Analysis Report (PSAR) for the LAW Facility
states the following:
If offsite power is lost, the UPS will supply the exhausters for [a matter of seconds] (until the standby diesel generators are available and loaded). Only after a loss of the standby diesel generators would there be a significant draw on the UPS. . . .
The standby diesel generators referenced
above are provided for asset protection purposes and are currently classified
as non-ITS SSCs. However, the PSAR for
the LAW Facility explicitly cites the standby emergency generators as SSCs that
directly minimize challenges to the SDC UPS systems. The Board’s staff believes that in this context, the function of
the standby diesel generators meets the SRD definition of ITS and is
appropriate for RRC classification.
BNI representatives stated they will
evaluate both the lightning protection system and the standby diesel generators
for possible reclassification as RRC.
Radiation-Related Cable Degradation―Electrical cables employed in nuclear
facilities can suffer serious operational degradation as a result of prolonged
exposure to radiation. The current WTP
design calls for the use of modular cable sections in high-radiation areas in
the HLW and Pretreatment facilities.
These modular sections, known as jumpers, facilitate easy disconnection
and replacement of cable prone to radiation damage without the need to remove
and replace cables that remain undamaged by virtue of increased shielding or
distance from radioactive sources. This
approach has proven efficient and effective in other Hanford facilities. However, BNI representatives could not
provide any analysis or identify any standards or criteria that will be used in
determining the allowable cable lifetime as a function of the anticipated
radiation environments in the HLW and Pretreatment facilities. To help ensure the ability of SDC and SDS
cabling to perform adequately throughout its installed lifetime, the Board’s
staff suggested employing cable qualification principles found in Institute of
Electrical and Electronics Engineers (IEEE) Standard 383, IEEE Standard or
Type Test of Class ZE Electric Cables, Field Splices, and Connections for
Nuclear Power Generating Stations, a consensus industry standard that
contains requirements for safety-related cables installed in nuclear
environments. Application of these
principles would serve to establish a defensible cable lifetime limitation to
be used in the eventual WTP high-radiation cable replacement regime.
Sizing Margins for Emergency Diesel
Generators―Sizing of
emergency diesel generators is an iterative process that will culminate in July
2003, when the generators are slated for procurement. A nominal 25 percent spare capacity is to be built into the
ultimate procurement specification, of which 10 percent will be dedicated to
load growth, 10 percent to uncertainty, and 5 percent to normal electrical
losses. At this stage of the design,
with significant load changes (stemming from the emergency load train and melter
rearrangements discussed above) expected in the near future, the magnitude of
the total load that will have to be supplied by the emergency diesel generators
is uncertain. The Board’s staff is
concerned that if major design changes are made subsequent to diesel generator
procurement, significantly more than 10 percent of the overall margin could be
used to accommodate short-term load additions, thereby leaving inadequate spare
margins for uncertainty and electrical losses.
Instrumentation and Control Systems. The
following concerns were noted by the Board’s staff with regard to ITS I&C
systems.
Important-to-Safety Digital Controls―The staff began its review of the control
system used to initiate safety-related automatic protective actions. This system, called the programmable
protection system (PPS), will be designed to meet all ITS automated control
responses. In conducting its review,
the staff found that the design standard currently identified for the PPS would
allow higher failure rates than are currently found in similar nuclear
applications. At this time, the PPS
hardware has not yet been procured, and the actual system performance could
well exceed the minimum cited in the current design standard. The staff will review the PPS specification
once a procurement decision has been made to evaluate the adequacy of the
system reliability.
High-Level Waste Melter and Offgas Systems―The staff reviewed the status of the HLW
melter and offgas systems, which are designated as SDS because they are the
primary boundary for confinement of hazardous material, and they are the second
physical barrier for severity level-l and -2 events. The staff determined that the melter and offgas system models had
not been exercised with anticipated system pressure surges in combination with
single failures, such as an exhaust fan stopping or an exhaust valve closing. The contractor stated that additional
analysis was planned, with an expected completion date of October 2003, to
verify the adequacy of the design under all anticipated conditions. The Board’s staff intends to review the
results when they are available.