[DNFSB LETTERHEAD]
July l0, 2003
The Honorable Everet H. Beckner
Deputy Administrator for Defense Programs
National Nuclear Security Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0104
Dear Dr. Beckner:
The staff of the Defense Nuclear Facilities
Safety Board (Board) recently conducted a review of hoisting and rigging
operations at the Pantex Plant. A
number of significant deficiencies were identified by the site contractor, BWXT
Pantex, and the Pantex Site Office following the recent hoisting occurrence in
the mass-properties facility at the site.
The Board’s staff noted issues, including improper maintenance of
safety-class hoists and inconsistent training, as discussed in the enclosed
report.
A number of corrective actions are in
various stages of planning and implementation to address the identified
issues. Although it is too early to
judge the effectiveness of the proposed corrective actions, the Board remains
concerned and urges prompt attention to this important safety program.
Therefore, pursuant to 42 U.S.C. § 2286b(d), the Board requests a status
briefing within 120 days of receipt of this letter or when a final set of
corrective actions for the issues noted in the enclosed report has been clearly
defined and funded-whichever occurs sooner.
Sincerely,
John T. Conway
Chairman
c:
Mr. Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff Issue Report
June 20,
2003
MEMORANDUM FOR: J.
K. Fortenberry, Technical Director
COPIES: Board
Members
FROM: J.
Shackelford, C. Shuffler
SUBJECT: Hoisting
and Rigging at the Pantex Plant
This report documents a review of the
hoisting and rigging program at the Pantex Plant, conducted during the week of
May 26, 2003. Members of the staff of
the Defense Nuclear Facilities Safety Board (Board) J. Shackelford and C.
Shuffler, together with outside expert R. West, evaluated the site’s hoisting
and rigging program, focusing in depth on the root-cause analysis, corrective
actions, and lessons learned from recent hoist-related occurrences. Other major areas of the review included the
following:
BWXT’s review of the January 2003 hoist
brake failure in Building 12-60 revealed several significant deficiencies in
the hoisting and rigging program. In
response to the review, BWXT and the Pantex Site Office (PXSO) established several
corrective action programs to address needed improvements. The Board’s staff found these programs to be
in various stages of development, approval, and implementation, but noted that
there is no clear indication that resources and funding are available to
complete them. The staff also identified
some additional issues that had not been addressed.
Codes and Standards. The
Board’s staff reviewed the codes and standards in the BWXT contract related to
hoisting and rigging and found that the majority of the applicable industry
guidance is appropriately referenced in the standards/requirements
identification documents (SRIDS).
However, one significant exception involved American Society of
Mechanical Engineers (ASME) NOG-1, Rules for Construction of Overhead and
Gantry Cranes. Department of Energy
(DOE) Guide 420.1-1, Nonreactor Nuclear Safety Design Criteria and Explosive
Safety Criteria, requires the use of ASME NOG-1 for the construction of
safety-significant and safety-class cranes.
The Board’s staff observed that this standard was not referenced in the
SRIDS, and that BWXT had not evaluated the safety-class hoists and cranes at
Pantex with respect to the guidance contained in the standard. BWXT personnel acknowledged the staffs
concern and committed to evaluating the safety-class hoisting equipment using
ASME NOG-1.
Safety Classification.
BWXT’s current authorization basis classifies the 83 facility hoists
used for nuclear explosive operations as safety-class equipment. The requirements for this equipment are set
forth in Design Feature (DF) 3 of the site Technical Safety Requirements
(TSRs). The DF requires the hoists and
cranes to be designed and installed in accordance with applicable sections of
29 Code of Federal Regulations (CFR) 1910.179 and the ASME B30 series for load
rating, brakes, and stops.
The current documented safety analyses for
Zone 12 facilities, which have been approved by DOE but not yet implemented by
the site, postulate swinging impacts involving weapons traveling at the maximum
horizontal speed that BWXT calculated that a facility hoist could reach under
normal operating conditions. However,
the hoists at Pantex are pneumatic, with the speed of travel being determined
by the inlet pressure to the hoists.
Although the hoists are designed to operate at lower pressures (i.e.,
less than 90 psig), the facilities’ compressed air system can deliver
significantly greater air pressures (i.e., in excess of 125 psig) under certain
circumstances. To date, the contractor
has been unable to determine the theoretical maximum hoist speeds at these
higher pressures.
BWXT has proposed revisions to the approved,
but unimplemented, authorization basis that would increase the maximum speed
used for the accident analyses, but these revisions cannot be completed until
new weapon response data are provided by the design agencies. The potential will still exist for the
installed equipment to exceed this new, higher maximum speed. As a result, BWXT is considering engineering
modifications to limit inlet air pressure, thus limiting the hoist travel
speed. The staff observed that no
implementation plan has been approved and funded to design and install any of
these modifications.
The Board’s staff also noted that the travel
stops installed on the equipment are not rated for the speeds that could be
encountered in the currently postulated scenarios involving a runaway
hoist. As a result, the staff
questioned whether the current approved, but unimplemented, accident analysis
is bounding with respect to the limiting impact scenarios.
Operations and Training. The
Board’s staff reviewed facility hoisting and rigging procedures and observed
operations in the training bays.
Additionally, the staff conducted interviews and discussions with
production technicians, system engineers, site management, and the training
staff concerning appropriate actions on the part of production technicians
during a postulated incident involving a runaway hoist. The staff noted significant inconsistencies
among the responses expected of production technicians by management, training,
and operations personnel during such an event.
During the January 2003 hoist brake failure
in Building 12-60, the production technicians lost the ability to control the
hoist with the pendant and resorted to guiding a nuclear explosive component
into its fixture manually. BWXT
management representatives indicated that they expected production technicians
to depress the stop button on the hoist pendant while simultaneously
dispatching a second technician to close the emergency shutoff valve supplying
air to the hoist. They did not expect,
or desire, production technicians to use other control functions on the pendant
to redirect the hoist. The training
staff, however, indicated that they trained production technicians to use all available
means, including redirecting the hoist with other pendant control functions, to
regain control of a malfunctioning hoist.
The Board’s staff interviewed production technicians during two separate
simulated hoisting operations, and received two different responses regarding
the actions each production technician would take during such a scenario. Further, the Board’s staff observed that
system engineering personnel had not evaluated the runaway hoist scenario with
respect to expected equipment performance.
The Board’s staff noted that BWXT has had more than 4 months since the
actual brake failure incident to implement appropriate corrective actions and
remedy any confusion about the desired response of production technicians
during this type of failure. BWXT
personnel acknowledged this training deficiency and are currently working to
resolve it.
Review of the Building 12-60 Hoist Brake
Failure, Root-Cause Analysis, and Corrective Actions. The
Board’s staff reviewed the operational aspects, root-cause assessment, and corrective actions
associated with the hoist brake failure in Building 12-60 that occurred on
January 10, 2003. The details of this
event are documented in Occurrence Report ALO-AO-BWXP-PANTEX-2003-0002. During the event, the facility hoist failed
to respond to operator actions intended to control a nuclear explosive unit
during lifting operations, and the unit slowly lowered to a resting
position. During the event, operators
took actions to secure the unit safely, and no adverse consequences or damage
occurred. However, the event revealed a
number of deficiencies in the hoisting and rigging program, as well as issues
related to root-cause analysis and corrective actions.
Immediately following the incident, BWXT
removed the hoist from service and performed a root-cause analysis to determine
the cause of the failure. At the time,
BWXT system engineers did not have detailed diagrams and manuals for this
safety-class hoist. Therefore, they
were unable to perform a rigorous failure modes and effects analysis (FMEA) to
support the root-cause analysis. As a
result, BWXT initially attributed the hoist failure to deficiencies in the
control pendant, a conclusion later determined to be incorrect. After this initial (incorrect) root-cause analysis,
the pendant was replaced, and the hoist was returned to service. Following additional questions and
discussion with PXSO and the hoist manufacturer, however, BWXT again removed
the hoist from service for further investigation. When the required drawings were received from the manufacturer,
almost 1 week after the incident, an FMEA was performed. It showed that the root-cause initially
identified by BWXT was not a credible failure mode.
During follow-up discussions with the
manufacturer, BWXT noted that this type of hoist had been subject to similar
failures in other applications. The
manufacturer had determined that a design deficiency existed in the brake
unit. This deficiency allowed a buildup
of brake dust to bind the brake piston in its housing, preventing application
of the brake. The manufacturer reported
that a modification was available to limit the effect of this dust
buildup. This modification was subsequently
made to the applicable hoists. Brake
inspections of the failed hoist revealed approximately 1 teaspoon of brake dust
in the unit. BWXT personnel
acknowledged that they had not been following the manufacturer’s recommendation
to disassemble, clean, and inspect the brake periodically. The root-cause analysis was subsequently
revised to reflect the fact that the primary cause of the incident was failure
to perform the manufacturer’s recommended maintenance, with a secondary,
contributing factor being related to the design deficiency.
BWXT determined that the initial root-cause
analysis had been based on inadequate technical information and had incorrectly
identified the cause of the failure. As
a result, an inadequate corrective action plan had been implemented, and the
hoist had been returned to service prematurely before the actual failure mode
had been corrected. BWXT is currently
working to upgrade the methodology supporting its corrective actions
process. The incident also revealed
significant weaknesses in BWXT’s program with respect to maintaining adequate
technical information and documentation, as well as communicating with vendors
to ensure that up-to-date information on operating experience is available for
safety-class equipment. Finally, the
event highlighted the need for significant improvements in BWXT’s efforts to
ensure that all of the manufacturer’s recommended maintenance is either
performed or appropriately evaluated for deferral or exclusion. The current corrective action plan for the
hoist brake failure in Building 12-60 addresses this issue for the safety-class
hoists at the Pantex Plant.
Maintenance and Procurement. As
noted above, BWXT concluded that it had not adequately implemented the
manufacturer’s recommended maintenance activities (or properly justified their
omission) for safety-class hoists. Upon
further review, BWXT determined that this problem existed with other vital
safety systems at the site and indicated that corrective actions were under way
to address this issue.
Following a request by the Board’s staff, it
was found that BWXT did not have an adequate program for trending equipment
failures and deficiencies. A report on
crane and hoist deficiencies for 1998–2002, generated in response to the staffs request, showed maintenance
problems and deficiencies in a variety of areas. Currently, no formal program exists to track and trend equipment
failures for the safety-class hoists, but BWXT committed to establishing such a
program in a corrective action plan.
Additionally, the Board’s staff noted that the site had only recently
incorporated predictive maintenance practices (e.g., lube oil analysis) into
the maintenance programs for vital safety systems.
An incident that occurred in March 2003,
involving the failure of draw cables for a lifting and rotating fixture,
illustrated a deficiency in the site’s procurement process. A cable had failed in an unexpected manner,
with the wire rope pulling out of the swaged end. Subsequent testing revealed that cables procured during the last
2 years had continued to fail in this unexpected manner and at loads
significantly below the manufacturer’s rating.
It was determined that the site had not implemented the appropriate
administrative mechanisms to ensure that the procured components would meet the
required quality control criteria. BWXT
is currently working to resolve this procurement problem.
Conclusion. The
Board’s staff noted a number of significant deficiencies in the Pantex Plant’s
hoisting and rigging program. Most of
these issues had been identified by BWXT and PXSO prior to the visit by the
Board’s staff. A number of the
deficiencies are generic in nature and applicable to other vital safety systems
and program areas. Although corrective
actions have been initiated or are being developed for these issues, there is
no clear indication that resources and funding are available to complete all of
the required actions. In view of the
actions remaining to be accomplished, the Board’s staff will continue to follow
resolution of these issues closely.