
- Employees are not encouraged to receive CPR training and certification or
to get recertified.
- Employees were not knowledgeable about the indications for initiating CPR
and about techniques of CPR.
- Lay rescuers demonstrated extreme bravery in proceeding with the rescue of
the accident victim in the face of obvious danger.
- Lay rescuers did not positively ensure that all energy sources were
de-energized before administering first aid.
- The current 911 system for LANL is not adequate to meet a demand of two or
more calls at the same time.
- Emergency medical technician personnel did an exemplary job of
transporting the accident victim as rapidly as possible to the Los Alamos
Medical Center and in administering appropriate treatment on the scene and en
route.
- Los Alamos Fire Department emergency medical technicians are not currently
trained or certified in the administration of cardiac medications.
- LAAO did not require LANL personnel to preserve the scene of the accident
until the Board arrived at the scene.
- The physical evidence pertinent to the accident was not gathered,
inventoried, and controlled in a disciplined, documented manner.
- LAAO did not require JCI, LANL, and the Type B Accident Investigation
Board to establish a documented chain of custody for the physical evidence
pertinent to the accident.
Probable Causes
- The Los Alamos Fire Department's concern for the cost of training
emergency medical technicians to administer cardiac medications versus the
number of cardiac patients who would need such services has prevented the
technicians from receiving this training.
- Resource constraints have reduced the capability of Protective
Technologies-Los Alamos to receive 911 calls and radio dispatch assistance
simultaneously.
- CPR training does not provide sufficient practice in the indicators of
cardiac arrest and application of CPR techniques.
- Deficiencies in emergency response training exist in regard to positively
identifying the absence or disconnection of stored energy sources prior to
administering first aid.
- LAAO did not recognize the need to preserve and document the physical
conditions of the accident scene.
- LAAO personnel were not trained in DOE accident investigation techniques,
processes and procedures.
- There is no procedure requiring LAAO to train accident investigation team
leaders.
Findings
- Emergency response time by the JCI Utilities Power Control Section is a
minimum of one hour during non-standard working hours.
- A JCI job-specific procedure identifies the use of personal protective
equipment to be used during jackhammering.
- Personal protective equipment training and certification, as prescribed in
JCI ES&H Manual Procedure 12-29-040, provides for the basic (but not all)
requirements of 29 CFR 1910.132 (f) (1-4).
- Safety training for the accident victim, as required by JCI ES&H
Manual Procedure 12-29-040, was not completed prior to the accident.
- 29 CFR 1926.416 (a)(3) requirements were not met by JCI at the accident
work site in Building TA-21-209.
- The JCI Utilities Power Control Section has developed formal Utility
Operating Instructions, which were implemented accordingly by all JCI Utilities
Power Control Section electrical workers on the day of the accident.
- The JCI Utilities Power Control Section has developed job-specific
lockout/tagout procedures (UOI 63-00-180, "Clearances") for
high-voltage work that satisfy industrial standards and which were appropriately
implemented the day of the accident.
- The rubber gloves worn by the accident victim during concrete cutting work
on January 16, 1996, at Building TA-21-209 did not comply with the JCI Procedure
12-25-008 or 29 CFR 1910.137 testing requirements for such gloves.
- The public address system in Building TA-21-209 is not connected to any
form of uninterruptible power supply.
- The design drawings for the Waste Stream Corrections Project did not
comply with the design requirements of DOE Order 6430.1A, Section 16.
- Adequate electrical engineering design support was not provided for the
Waste Stream Corrections Project.
- LANL Occurrence Report ALO-LA-LANL-HRL-1994-0004 was officially closed
without JCI completing the required corrective actions.
- The JCI Roads and Grounds Pre-Job Safety Checklist does not address
electrical hazards.
- The LANL small job ticket/work ticket addresses electrical hazards in the
ES&H review section only where the voltage exceeds 480 volts.
Probable Causes
- An emergency plan for critical power needs does not exist to provide
guidance to JCI maintenance personnel responding to unscheduled power outages
and providing temporary electric power by portable generators to meet
building-critical needs.
- Backshift support for emergency electrical utilities service was
eliminated because of funding.
- A formal, complete, comprehensive electrical safety program document for
LANL or JCI is not in place.
- JCI did not recognize the need to prepare a procedure to reflect the
requirements of 29 CFR 1926.416(a)(2).
- JCI did not incorporate all the requirements of 29 CFR 1910.132(f)(4) into
its procedure.
- The JCI procedure requiring certification and training involving personal
protective equipment did not appear in the JCI ES&H Manual until November
28, 1995.
- JCI personnel misinterpreted the excavation permit requirements.
- JCI Utilities Power Control Section personnel at all levels have accepted
their job-specific operating instructions as procedures and requirements.
- JCI Safety and Maintenance personnel do not routinely perform safety
inspections of maintenance activities.
- JCI ES&H Manual Procedure 12-25-008 does not satisfy the requirements
of 29 CFR 1910.137 for rubber glove testing.
- The JCI Maintenance organization does not have a systematic program for
keeping track of rubber glove test dates, retest due dates, or inventory
control.
- LANL policies and requirements are not factored into JCI procedures and
policies.
- The validation process for closure of corrective action items identified
in LANL occurrence reports is not effectively implemented.
- Lessons learned from previous electrical incidents have not been
effectively implemented into LANL or JCI procedures or training programs.
4.3.1 Work Planning
Findings
- Administrative Requirement 1-10, "Environment, Safety, and Health
Questionnaire," has not been revised to reflect the use of the ESH
Identification process.
- The ESH Identification process is ad hoc, was never approved formally by
LANL senior management, and is inconsistent with the management-approved
Administrative Requirement 1-10 procedure.
- All subject matter expert comments on the ESH Identification Project
Summary were not resolved prior to the initiation of the Waste Stream
Corrections Project, in accordance with the requirements contained in
Administrative Requirement 1-10, "Environment, Safety, and Health
Questionnaire."
- The Risk Assessment Group review of the Waste Stream Corrections service
request for ES&H concerns did not identify all hazards associated with the
Waste Stream Corrections Project.
- Procedures are not in place to define the ES&H requirements to be
accomplished by Risk Assessment Group in its review of service requests, small
job tickets/work tickets, or other documents used to authorize and/or control
JCI work activities.
- Although the Water Quality and Hydrology Group made commitments regarding
plans for organizing the Waste Stream Corrections Project to address ES&H
issues, those commitments were never fully met or implemented.
- In utilizing a tailored small job ticket/work ticket form for the Waste
Stream Corrections Project, LANL ES&H staff omitted the ES&H review
section, with no reasonable assurance that ES&H reviews would be
accomplished either by the LANL Risk Assessment Group or JCI.
- JCI craft supervisors did not conduct a preliminary hazard analysis for
the work in Building TA-21-209, as required by JCI procedures.
- JCI craft supervisors were not familiar with the requirement, procedure,
or form for conducting preliminary hazard analysis prior to any work activities
involving JCI personnel.
- JCI craft workers involved in the accident had not been provided with
formal documentation on the scope or safety review/ requirements for the work
they were to perform.
Probable Causes
- Administrative Requirements have not been kept up to date to reflect
changes in LANL organizations, procedures, and practices.
- Laboratory-wide procedures have not been developed to establish
performance expectations and define the requirements for conducting work
planning and control within various LANL organizations.
- LANL does not have a good internal assessment process to discover
deviations from procedures.
- There is neither enforcement of safety requirements by LANL or JCI
management, nor accountability for poor safety performance.
4.3.2 Procedures
Findings
- Laboratory-wide operating procedures have not been written for a majority
of the Administrative Requirements, which is in violation of Director's Policy
102. Specific to this incident, there are no Laboratory-wide operating
procedures to implement the Director's Policies for (1) conduct of operations,
(2) configuration management, (3) work planning and control, and (4) ES&H
design reviews.
- LANL management has allowed Laboratory personnel at the Division and/or
Group level to ignore or change requirements without revising applicable
procedures.
- Line managers did not ensure that Administrative Requirement 1-11 was met.
Forms other than the "approved" work control forms were used to issue
work. Standing Work Orders were being used for non-routine, non-repetitive
tasks, in direct conflict with Administrative Requirement 1-11 and with their
intended purpose.
- LANL and JCI staff were not aware that an excavation permit was required
by Administrative Requirement 1-12.
- The Administrative Requirements contained in the LANL ES&H Manual are
not well understood or complied with by either the staff or management levels
within LANL.
- The requirements of SPI 12-02-010, "Work Order Review," were
not complied with.
- There is no single, comprehensive work control procedure that describes
the flowpaths and requirements for submitting, approving, and issuing work
through LANL and subcontractors contracted to perform work (JCI in this case).
- The stop-work order notice was not on file, as required by Director's
Policy 116, in any of the four Division offices that were checked nearly one
week after its issuance.
- There was no verification that all appropriate personnel received the
stop-work order notice.
- Procedures did not exist for many of the processes needed to support the
Waste Stream Corrections Project, and where procedures did exist and were
available for use by LANL and JCI personnel, they were considered as optional
guidance and were not generally followed.
Probable Causes
- Administrative Requirements do not reflect the current LANL organization,
and confusion exists as to specific organizational responsibilities.
- High-level procedures are written and requirements are directed to line
managers without adequate infrastructure, responsibility, and accountability to
implement the numerous requirements.
- LANL senior management does not enforce the requirements described in the
Administrative Requirements, Director's Policies, and other procedures, thereby
permitting Division and Group level management to interpret, change, or violate
procedures when the need exists.
- There was a widespread misconception within both LANL and JCI
organizations that excavation permits were only required for outside activities.
- The excavation permit procedures only require the performance of a utility
survey and Risk Assessment Group review. There is no requirement for a review
of drawings or a physical check for electrical or piping penetrations at the
work sites.
- Standing Work Orders are being used for complex, non-repetitive,
non-routine work.
- The master management e-mail method used to promulgate the sitewide
stop-work order does not incorporate message receipt confirmation. The process
is "open loop" and does not assure the stop-work order notice is
received and placed in effect.
4.3.3 Design and Configuration Management
Findings
- Preliminary design documents were used for construction activities.
- Design reviews for the Waste Stream Corrections Project work did not
comply with the design review requirements contained in Administrative
Requirement 1-14 and the Quality Management Plan for 10 CFR 830.120.
- The process for obtaining approval for design changes is informal and does
not require field verification of changes requested prior to approval.
- The LANL configuration management program is ineffective at maintaining
configuration control of facilities.
- As-built drawings are not required to be updated for facility
modifications, particularly those "modifications" being handled as
maintenance activities.
- The Water Quality and Hydrology Group did not recognize its
responsibilities for design review after assuming the project lead role.
- The graded approach in the configuration management program does not
require controls for non-vital systems.
Probable Causes
- LANL management has not instituted Laboratory-wide procedures outlining
organizational responsibilities and authorities governing the conduct of design
reviews.
- High-level procedures are written, and requirements are directed to line
managers without adequate infrastructure, responsibilities, and accountability
to implement the numerous requirements.
- Management does not uniformly enforce the requirements described in
Administrative Requirements and Director's Policies.
- There is no Laboratory-wide configuration control procedure.
- Modifications to facility systems are not being captured or analyzed
against the existing safety analyses or system design documents.
4.4 PERSONNEL RESOURCES AND TRAINING
Findings
- JCI did not provide job-specific electrical safety-related work practice
and personal protective equipment training commensurate with DOE orders, OSHA
regulations, or its own procedural requirements.
- Oversight by LANL to measure the contractual requirement deliverables for
training at JCI evaluates only high-level programmatic issues.
- The training process at JCI for critical courses and activities is not
completely directed and implemented as required by the JCI Training Manual and
JCI Standard Practice Instructions.
- Training requirement principles that appear in DOE Order 5480.20 and the
training requirements of DOE Order 4330.4B are not completely implemented in all
critical training courses and activities at JCI.
- JCI crafts personnel and union stewards have concerns about raising safety
issues to foremen and supervisors because they fear recrimination.
Probable Causes
- The training oversight measurement metrics established for LANL are broad
and vague.
- The JCI safety and training organizations do not fully integrate their
respective procedure requirements.
- JCI resource constraints have prevented the complete implementation of the
training requirements commensurate with DOE orders.
- Supervisors and foremen are not being held accountable or being
disciplined by JCI management for trying to subvert the workers' rights to raise
safety issues on construction or maintenance jobs.
4.5.1 Johnson Controls World Services, Inc.
Findings
- Failure to categorize the work as construction resulted in removing the
administrative barrier of an independent safety review by the JCI construction
safety engineer, as well as conduct of both a preliminary hazard analysis and an
activity hazard analysis.
- Failure to prepare as-built drawings of electrical and other stored energy
system changes due to past facility modifications resulted in the loss of
configuration control of a potentially life threatening system.
- JCI does not have a documented process for work package assignment and/or
for detailing supervisor or foreman accountability to assure technical and
safety adequacy of the information provided in the work package.
- JCI does not routinely prepare design drawings for modifications to
existing buildings, particularly for work packages that flow from LANL through
the JCI Maintenance Division.
Probable Causes
- The Standing Work Order system does not require a safety review for
individual tasks performed under the work order.
- The Standing Work Order system is used as a convenient method for
performing work without preparing a job ticket.
- The safety-related implications of maintaining configuration control of
stored energy systems is not recognized.
4.5.2 Santa Fe Engineering
Findings
- SFE preliminary drawings did not consider electrical system tie-in
requirements.
- SFE preliminary drawings were not adequate as a basis to perform
construction activities in a safe manner.
- SFE provided guidance/concurrence on sump pump relocation informally
without considering engineering or safety significance.
- SFE preliminary drawings did not identify all potential hazards identified
in existing facility drawings which were available.
Probable Causes
- The SFE "field engineer" was not a degreed engineer with
electrical system knowledge and experience.
- The LANL contract with SFE did not reflect the need for detailed drawings
or level of engineering safety expertise needed to support the expectations of
LANL management.
4.5.3 Los Alamos National Laboratory
Findings
- The LANL processes used in managing the modification of the building
systems did not comply with the LANL Quality Plan or DOE Order 6430.1A.
- Management is allowing the Standing Work Order system to be used for
non-routine, non-repetitive tasks without adequate safety review.
- The current use of the Standing Work Order system is in conflict with the
original intent of the concept.
- Conduct of operations at LANL does not comply with DOE Order 5480.19;
there is insufficient formality of operations to assure that management's
expectations are being met.
- The implementation of a Laboratory-wide conduct of operations program at
LANL has not received sufficient management attention.
- Design processes are not uniform throughout LANL, and the management-level
controls applied in these processes do not ensure that worker safety and
operational needs are being met in the design processes.
- The Engineering Sciences and Applications Division did not meet its line
responsibility for managing changes to the facility.
- The Facility Management Unit process is in a transitional state where
roles, responsibilities, authorities, and accountabilities are not well
understood throughout LANL organizations.
- Administration of the Waste Stream Corrections Project corrective actions
did not comply with Director's Policy 124.
- The processes for determining and assigning work management-level
classifications do not provide consistent results at LANL.
- The work being performed at the accident site should not have been
classified as Management Level 4 by the Facilities Support Operations Group,
because of the type of work involved, the complexity, and the necessity to
comply with EPA regulations.
- The design controls required by the assigned Management Level 4
classification do not require adequate configuration management, design, and
turnover of systems.
- The lessons learned from previous significant accidents have not been
implemented at LANL to eliminate programmatic deficiencies that have repeatedly
been identified as either root or contributing causes to the accidents.
- LANL management programs have not been effective in holding individuals
accountable for completing assigned tasks, particularly those involving
corrective actions related to programmatic deficiencies identified during
assessments.
- The Laboratory Director has not formally promoted the Facility Management
Unit model to the management team.
- LANL management is not ensuring that the rights of LANL subcontractor
employees to a safe work environment are being protected.
Probable Causes
- Responsibility for the design and construction of NPDES modifications was
transferred to a support organization that did not have the necessary and
sufficient engineering or project management tools and experience to perform the
required tasks to assure safety during field construction.
- The Standing Work Order process does not require a safety review for
individual subtasks performed under the overall Work Order.
- The Standing Work Order process is utilized by LANL personnel as a
convenient method of performing work without a job ticket and work package,
allowing most work to be field directed.
- The Facility Management Unit responsible for Building TA-21-209 did not
take an active role in the design, development, or field implementation of the
Waste Stream Corrections modifications being managed by the Water Quality and
Hydrology Group.
- The decision supported by LANL Division and Group level management to "fast
track" Waste Stream Corrections modifications in an undocumented process
seriously reduced the margin of safety for the accident victim by eliminating
engineering and safety reviews and by not providing sufficient details in the
field work package.
- LANL management has not placed a high priority on the implementation of
conduct of operations.
- Management is not directing program or procedure compliance in a top-down
approach; consequently, organizations create their own systems in order to
accomplish their assigned functions.
- Management has not adequately considered the importance of providing
appropriate detail in work packages and preparing modifications to as-built
drawings for subsequent safe operations and maintenance of facility systems.
- There are different criteria for establishing work management level
classifications in the two procedures reviewed, and the guidance for assigning
risk in each of the LANL work classification procedures is too vague to assure
consistent classification of work management level classifications between
organizations.
- The LANL Facility Management Unit model has not received formal direction
from LANL senior management and, as a result, is not fully implemented across
the Laboratory.
- LANL management does not assign adequate priority to the implementation of
corrective actions that are needed to improve safety at the Laboratory, and does
not hold individuals accountable for safety performance.
- LANL managers have not recognized the importance of implementing formal
processes to ensure consistent operations.
- LANL managers have not provided an environment that encourages
subcontractor employees to raise safety issues.
4.5.4 Los Alamos Area Office
Findings
- LAAO management reassigned the Facility Representative from Technical Area
21 to other activities for most of the 1995 calendar year.
- LAAO Facility Representative personnel do not understand the "teaming
concept" and whether or not it affects their responsibilities and
accountabilities for line management safety oversight of LANL.
Probable Causes
- LAAO management reassigned the Facility Representative to Technical Area
55 and to other temporary assignments in an attempt to allocate scarce resources
in a priority manner. Technical Area 55, Readiness Assessments and Accident
Investigations, was given priority over day-to-day oversight at the Tritium
Facilities, which included Building TA-21-209.
- The scope of the "teaming concept" has not been adequately
defined and explained to LAAO personnel to ensure that it does not inhibit the
performance or objectivity of day-to-day line management oversight.
4.5.5 Albuquerque Operations Office
Findings
- The Functional Area Appraisal Procedure developed by AL to implement the
pilot oversight program requires agreement from the contractor on all findings.
- The Functional Area Appraisal Procedure reduces the independence and
effectiveness of the assessment team.
Probable Cause
The Functional Area Appraisal Procedure is not consistent with the
definition of the program provided by the Deputy Secretary of Energy.
4.5.6 DOE Headquarters
Findings
- The EH Resident Office was not staffed to the level originally planned.
- The EH Resident's surveillance duties have been reduced because of other
priorities.
- The single Los Alamos EH Resident does not possess all of the education
and experience required to provide effective oversight of all of the major
activities at LANL.
Probable Causes
- Staffing constraints did not allow the EH Resident Office to be fully
staffed as originally planned.
- Work priorities for the Los Alamos EH Resident are not well defined or
understood.
Findings
- LANL and JCI personnel did not correctly characterize the Waste Stream
Corrections Project as a construction activity.
- LANL and JCI personnel did not conduct surveys, or make other reasonable
efforts, to determine the location of underground utility installations prior to
opening the excavation in the basement of Building TA-21-209.
- JCI did not ensure that a hazard assessment was conducted prior to work on
elements of the Waste Stream Corrections Project and, in particular, prior to
work in the basement of Building TA-21-209.
- LANL and JCI management did not ensure the establishment of adequate
industrial hygiene control measures for the protection of employees during the
mechanical removal of tuff in the basement of TA-21-209.
Probable Causes
- LANL and JCI personnel incorrectly interpreted the scope of work involved
in the Waste Stream Corrections Project.
- LANL and JCI personnel were unfamiliar with procedural requirements and,
consequently, failed to ensure the enforcement of procedural requirements during
the conduct of work.
- Inadequacies existed in LANL and JCI ES&H organizational reviews of
work packages that could have identified potential hazards in the workplace.
- There was a lack of LANL facility line management involvement in planning
and execution of the Waste Stream Corrections Project.


Please send comments to support@tis.eh.doe.gov
Last Modified: Friday, 28-Feb-97 10:09:00