Technical Safety Requirements
Draft 3/1/06
FUNCTIONAL AREA GOAL: Contractor has developed,
maintained, and received DOE Field Office Approval for the
necessary operating conditions of a facility. The facility has
also maintained an inventory of safety class and safety
significant systems and components.
REQUIREMENTS:
- 10 CFR 830.205, Nuclear Safety Rule.
- DOE-STD-3009-2002, Preparation Guide for U. S.
Department of Energy Nonreactor Nuclear Facility Documented
Safety Analyses.
- DOE-STD-1186-2004, Specific Administrative Controls.
GUIDANCE:
- DOE G 423.1-1, Implementation Guide for Use in
Developing Technical Safety Requirements.
- NSTP 2003-1, Use of Administrative Controls for Specific
Safety Functions.
Performance Objective 1: Contractor Program
Documentation: Summarize safety-significant SSCs and other
aspects of defense in depth that requires TSR coverage. The
scope of the TSR coverage is determined by the degree to which
barriers or the facility-safety basis are seriously
challenged.
Criteria:
- Provide for each category 2 or 3 nuclear facility
assurance that the TSRs as well as future changes are
approved by DOE.
- Provide for each category 2 or 3 nuclear facility
assurance that the TSRs are derived from the documented
safety analysis.
- Provide similar documentation that all safety class and
safety significant systems are linked to appropriate TSRs.
- Provide assurance for each category 2 or 3 nuclear
facility that the TSRs have sections on:
- Safety limits
- Operating limits, e.g. limited control settings (LSC)
and limited conditions for operation (LCO)
- Surveillance requirements
- Administrative controls
- Design features
- Use and application
Suggested
lines of inquiry and review approach for this performance
objective
Performance Objective 2: Contractor Program
Implementation
2.1 TSRs: Summarize safety-significant SSCs and
other aspects of defense in depth that requires TSR coverage.
The scope of the TSR coverage is determined by the degree to
which barriers or the facility-safety basis are seriously
challenged.
Criteria:
- Provide for each category 2 or 3 nuclear facility
assurance that the TSRs as well as future changes are
approved by DOE.
- Provide for each category 2 or 3 nuclear facility
assurance that the TSRs are derived from the documented
safety analysis.
- Provide similar documentation that all safety class and
safety significant systems are linked to appropriate TSRs.
- Provide assurance for each category 2 or 3 nuclear
facility that the TSRs have sections on:
- Safety limits
- Operating limits, e.g. limited control settings (LSC)
and limited conditions for operation (LCO)
- Surveillance requirements
- Administrative controls
- Design features
- Use and application
Suggested
lines of inquiry and review approach for this performance
objective
2.2 Administrative Controls: Administrative
controls can be used to address specific accident scenarios to
establish limiting conditions of operation (LCO).
Criteria:
- Provide ACs to prevent inadvertent criticality developed
by qualified personnel, reviewed by competent reviewers, and
correctly incorporated and implemented in facility
procedures.
- TSRs may also be provided for safety management programs
in the form of TSR ACs to support adequate defense-in-depth.
Such all-encompassing TSRs should be used in lieu of
individual TSRs for numerous specific aspects of programs
unless the control is significant to specific accident risk
reduction.
- Identify specific administrative controls (SAC) needed
to prevent or mitigate an accident scenario as appropriate.
In general, SAC designation based on worker safety are
limited to those administrative controls that would have
been safety-significant had that safety function been
provided by a safety-significant SSC. The established
hierarchy of hazard controls requires that engineering
controls requires that engineering controls with an emphasis
on safety-related SSCs be preferable to ACs or SACs due to
the inherent uncertainty of human performance.
Suggested
lines of inquiry and review approach for this performance
objective
Performance Objective 3: DOE Line Management
Oversight
Line management should be committed to manage and maintain
up to date TSRs.
Criteria:
- Line management should be committed to manage and
maintain up to date TSRs.
Suggested
lines of inquiry and review approach for this performance
objective