Readiness Review Program
Draft 12/15/2006
FUNCTIONAL AREA GOAL: DOE/NNSA Headquarters and Field
organizations and their contractors responsible for the
startup and operation of nuclear facilities have defined and
implemented contractual requirements to manage, evaluate, and
approve the startup and restart of nuclear facilities and
activities.
REQUIREMENTS:
- DOE Order 425.1C, Startup and Restart of Nuclear
Facilities
- DOE P 450.4, Safety Management System Policy
- DOE/NNSA Safety Management Functions, Responsibilities
and Authorities Manual
GUIDANCE:
- DOE-STD-3006-2000, Planning and Conduct of Operational
Readiness Reviews
- DOE-HDBK- 3012-2003, Operational Readiness Review Team
Leaders Handbook
- DOE G 450.4-1B, Integrated Safety Management System
Guide
Performance Objective 1: Contractor Program
Documentation
Contracts between DOE/NNSA and the contractors who operate
DOE/NNSA nuclear facilities contain adequate requirements
concerning management, evaluation and approval of the startup
and restart of the nuclear facilities and activities.
Contractors have developed comprehensive processes/procedures
for performing Operational Readiness Reviews (ORRs) and
Readiness Assessments (RAs).
Criteria:
- 1. The contracts with contractors who operate DOE/NNSA
nuclear facilities contain requirements for the startup and
restart of nuclear facilities.
- 2. Contract management processes require periodic review
to ensure the contracts are accurate and define requirements
for all work associated with the startup and restart of
nuclear facilities and activities.
- 3. DOE/NNSA contractors who operate nuclear facilities
have a formal process to flowdown contract requirements into
implementing processes/procedures to ensure that the
contract requirements for startup and restart of nuclear
facilities and activities are fully met.
- 4. DOE/NNSA contractors who operate nuclear facilities
have developed implementing processes/procedures for startup
and restart of nuclear facilities and activities that fully
comply with contract requirements including:
- Planning to achieve readiness to commencing nuclear
operations.
- Preparation and submittal of a Startup Notification
Report (SNR) that meets the following:
- Submitted at least annually, recommended quarterly,
and projects at least 1 year ahead.
- Includes every startup or restart, other than routine
resumption after a short, planned interruption
- Updates information from previous SNRs
- Brief description of operation or facility to be
started or restarted. For substantial modifications,
description of modifications and safety basis changes.
- Hazard Category of operation or facility
- Reason provided for non-operation/ shutdown and
duration since last operations
- Provides projected startup date
- Criteria for proposed type of review provided (e.g.,
ORR or RA)
- Requires basis/justification for type of review
- Identifies authorization authority
- Addresses review and approval, including DOE/NNSA
field office
- Line management preparation and approval of
readiness review Plans of Action (POA)
- Defines depth and breadth of review of ORR or RA.
- Addresses core requirements
- Written 4-6 months prior to startup
- Forwarding POAs to HQ for review, when required.
- Meets Order requirements
- Program requires Implementation Plans (IP) written
by the Team Lead.
- Develops criteria and review approach document to
fully assess scope defined by the POA.
- Identifies team members
- Meets Order requirements
- Line management process for achieving readiness and
self-assessments of readiness.
- Program addresses requirements and format of
completed assessment reports.
- Program addresses findings and observations, and
associated corrective action plans.
- Actions for requesting and obtaining approval to
start nuclear operations.
Suggested lines of inquiry and review approach for this
performance objective - tbd
Performance Objective 2: Contractor Program
Implementation:
The Contractor readiness review processes and procedures
are effectively implemented for startup and restart
activities.
Criteria:
- 1Contractors incorporate readiness activities into
long-range project planning and scheduling.
- The readiness review processes and procedures are
incorporated into the site Integrated Safety Management
System.
- SNRs are completed and approved with accurate and
complete descriptions of planned startups and restarts in
accordance with Contractor processes and
procedures.
- POAs are developed, reviewed, and approved 4-6 months
prior to the projected startup and in accordance with Order
requirements for defining the depth and breadth of the
review.
- Contractors plan, achieve, and verify readiness,
including the performance of a self-assessment prior to the
startup of the independent assessment process.
- Contractor Team Leads prepare for review and approval
IPs for readiness reviews that fully address the depth and
breadth defined by the POA, and in accordance with Order
requirements.
- Readiness review reports are prepared and issued in a
timely manner, fully describing the results of the
review.
- Corrective action plans for findings are formally
prepared, and activities tracked until completion.
- The Contractor Readiness Review processes/procedures
incorporate appropriate functions and principles of the Site
Integrated Safety Management System.
Suggested lines of inquiry and review approach for this
performance objective - tbd
Performance Objective 3: DOE/NNSA Line Management
Oversight:
DOE/NNSA HQ and Field/Site Offices provide effective
oversight of the contractor readiness review program through
their role in the review and approval of plans and reports,
and assessments of contractor's efforts in achieving
readiness, contractor self-assessments, and DOE/NNSA
assessments and daily oversight.
Criteria:
- 1. DOE/NNSA site and field offices have developed
written procedures that capture the requirements for startup
and restart of nuclear facilities.
- 2. DOE/NNSA site and field office procedures include the
following:
- Requiring, reviewing, and approving SNRs including:
- Evaluation criteria for adequacy, and
- Criteria for determining the appropriate level of
readiness review required.
- Determination of when an ORR and RA is required,
including the startup or restart of program work
associated with operating facilities when the new or
restarted program work does not require DOE approval of
changes to facility limits or requirements as stated in
authorization basis documents.
- Overseeing the contractor readiness activities
including responding to the contractor Readiness to
Proceed Memorandum.
- Evaluating of POAs and IPs when required, including
evaluation criteria.
- Supporting ORR and RA Teams when requested and as
appropriate.
- Conducting readiness reviews.
- Issuing authorization to start nuclear operations when
required.
- Tracking and verification of timely closure of
post-start findings.
- Forwarding documents such as SNRs, POAs, and IPs tHQ
for review when required.
Suggested lines of inquiry and review approach for this
performance objective - tbd